Or. Admin. Code § 137-049-0850 - Final Inspection

(1) Notification of Completion; inspection. The Contractor shall notify the Contracting Agency in Writing when the Contractor considers the Contract Work completed. Within 15 Days of receiving Contractor's notice, the Contracting Agency will inspect the project and project records, and will either accept the Work or notify the Contractor of remaining Work to be performed.
(2) Acknowledgment of acceptance. When the Contracting Agency finds that all Work required under the Contract has been completed satisfactorily, the Contracting Agency shall acknowledge acceptance of the Work in Writing.

Notes

Or. Admin. Code § 137-049-0850
DOJ 11-2004, f. 9-1-04, cert. ef. 3-1-05

Stat. Auth.: ORS 279A.065

Stats. Implemented: ORS 279C.570