Or. Admin. Code § 137-049-0890 - Contracting Agency Payment for Unpaid Labor or Supplies
(1)
Contract incomplete. If the
Contract is still in force, the Contracting Agency may, in accordance with ORS
279C.515(1), pay a valid claim to the Person furnishing the labor or services,
and charge the amount against payments due or to become due to the Contractor
under the Contract. If a Contracting Agency chooses to make such a payment as
provided in 279C.515(1), the Contractor and the Contractor's surety shall not
be relieved from liability for unpaid claims.
(2)
Contract completed. If the
Contract has been completed and all funds disbursed to the prime Contractor,
all claims shall be referred to the Contractor's surety for resolution. The
Contracting Agency shall not make payments to subcontractors or suppliers for
Work already paid for by the Contracting Agency.
Notes
Stat. Auth.: ORS 279A.065
Stats. Implemented: ORS 279C.515