25 Pa. Code § 965.4 - Eligible costs
Eligible costs include:
(1) Costs approved by the Board which are
necessary for construction of public sewerage facilities.
(2) Costs approved by the Board which are
necessary for construction associated with secondary treatment or advanced
treatment, or both.
(3) Costs
approved by the Board which are necessary for construction associated with
cost-effective alternatives to secondary treatment or advanced treatment, or
both.
(4) Costs approved by the
Board which are necessary for the construction of interceptor sewers.
(5) Costs approved by the Board which are
necessary for construction associated with the correction of an
infiltration/inflow problem.
(6)
Costs approved by the Board which are necessary for construction associated
with the rehabilitation or replacement of collector sewer systems only when the
applicant demonstrates that the collector sewer system is necessary to assure
the total integrity of the sewerage system.
(7) Costs approved by the Board which are
necessary for construction of new collector systems only when the applicant
demonstrates that sufficient treatment capacity exists.
(8) Costs associated with the completion of
the second opinion project review required under §
965.7 (relating to second opinion
project review).
(9) Other eligible
costs as defined under §
963.1 (relating to definitions)
which are approved by the Board, except that costs associated with the purchase
of land for rights of way or easements under the Uniform Relocation Assistance
and Real Property Acquisition Policies Act of 1970 (42 U.S.C.A. §§
4601-4655), are not eligible.
(10) Costs associated with the refinancing of
local debt incurred after March 5, 1985, only when the applicant demonstrates
the following:
(i) The construction started
after March 5, 1985, but before March 1, 1988.
(ii) The original debt was incurred to comply
with a State or Federal compliance schedule.
(iii) The project has met the requirements of
the Water Quality Act.
(iv) The
project has undergone an environmental review as required by the
Department.
(11) Costs
associated with the refinancing of local debt incurred after March 1, 1988,
only when the applicant demonstrates that it meets the requirements of §
963.17 (relating to funding
limitations).
(12) Costs approved
by the Board which are necessary for the implementation of a nonpoint source
project or estuary protection project.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.