Tenn. Comp. R. & Regs. 0400-46-01-.03 - PROGRAM MANAGEMENT
(1) The assigned
Project Criteria Points and the calculated Priority Point Value are applicable
only to WWTP projects and will be summed to establish a proposed project's
Priority Rank. Projects will be placed on the Priority Ranking List in
ascending order by Priority Rank, i.e., in descending order by total project
priority points.
(2) When the
project is placed on the Priority Ranking List, the potential loan recipient is
responsible for providing a written detailed project description, a schedule of
events, and an up-to-date project cost estimate to the Department. The
Department may request adjustments to the cost estimate at its
discretion.
(3) The Department will
use the project cost estimates on the Priority Ranking List to allocate
available funds to as many potential loan recipients as possible in order to
protect public health and the environment. The Department may limit the award
amount per loan in order to provide funds to more potential loan
recipients.
(4) The priority of
available funds will be assigned to those projects with the highest Priority
Rank on the Priority Ranking List with preference given to those projects that
are ready to proceed.
(5) The
Department may bypass projects on the Priority Ranking List that are not ready
to proceed. The Department may also bypass projects if a completed loan
application has not been received within 90 days after notification from the
Department to the potential loan recipient that failure to submit the completed
application will result in a bypass.
(6) Proposed projects with a lower Priority
Rank may be fundable by virtue of bypass. Preference will be given to those
lower-ranked projects that are ready to proceed and that will make progress
towards compliance with the enforceable requirements of the Clean Water Act and
the Tennessee Water Quality Control Act.
(7) Projects may be purged from the Priority
Ranking List annually, on April 15. Projects may be reinstated to the Priority
Ranking List upon the Department's receipt of a letter requesting the
reinstatement. The letter must also include a written, detailed project
description and an up-to-date project schedule and cost estimate.
(8) The Department will remove a project from
the Priority Ranking List prior to April 15 annually when financial assistance
has been awarded or upon receipt of a written request from the potential loan
recipient that they no longer want to include their project on the Priority
Ranking List.
Notes
Authority: T.C.A. ยงยง 68-221-801 et seq., 68-221-1001 et seq., and 4-5-201 et seq.