12-037 Code Vt. R. 12-030-037-X - VERMONT DAM SAFETY RULE
This rule is adopted by the Vermont Agency of Natural Resources pursuant to 10 V.S.A. Chapter 43, in particular § 1110.
The purpose of this rule is to provide guidance on the implementation of 10 V.S.A. Chapter 43 regarding the inventory, inspection, and evaluation of dams in Vermont. This includes guidance regarding the regulation and Agency oversight of dams under the jurisdiction of the Department of Environmental Conservation, including dams the failure of which may result in loss of human life, economic loss including property damage, lifeline disruption, and environmental damage. This rule also provides guidance regarding measures intended to protect public safety and provide for the public good through the proper planning, design, construction, reconstruction, enlargement, repair, alteration, breach, removal, inspection, operation, maintenance, monitoring, and supervision of dams and to provide for adequate margins of safety.
Any terms not defined in this section shall have the meaning given to the term by any Vermont statutes, rules, or policies governing the subject matter.
Agency means the Vermont Agency of Natural Resources
Appurtenant works means structures belonging to the dam and related to the dam's operation, including but not limited to, spillways, either in the dam or separate therefrom; the reservoir and its rim; low-level outlet works; and water conduits such as tunnels, pipelines or penstocks, either through the dam or its abutments.
Auxiliary Spillway means the secondary spillway not in use under normal conditions but used when needed to pass flood flows that exceed the capacity of the principal spillway.
Breached Dam means a dam that does not retain water or liquid but may or may not retain sediment under mean annual flow conditions with a hydraulic height of zero due to a partial dam failure or construction of a channel through or around a dam (i.e. dam maintains the reservoir drained under normal conditions).
Dam means any artificial barrier, including its appurtenant works, that is capable of impounding water, other liquids, or accumulated sediments.
A dam includes an artificial barrier that meets all the following:
A dam shall not mean:
Resources under Chapter 47 of this title;
Dam Breach Analysis means the analytical process of computing the flood hydrograph, resulting flood levels, and inundation area resulting from a simulated dam breach or failure.
Dam Crest means the top of the nonoverflow portion of the dam.
Dam Failure means a collapse of a dam resulting in the uncontrolled release of all or a portion of the reservoir contents.
Department means the Department of Environmental Conservation.
Dike means any appurtenant artificial barrier located on the same reservoir or waterbody as the dam that together with the dam impounds or is capable of impounding the reservoir. Typically, dikes are at saddle (low) points around a reservoir rim and do not include appurtenances such as spillways or low-level outlets. A dike is a dam.
Drainage Area means the total area that drains to a particular point on a river, stream, or reservoir.
Drained refers to the condition of a reservoir or impoundment where the water level is intentionally lowered below normal levels using appurtenant works such as a low-level outlet or temporary controls such as pumps or siphons. The dam remains in place and has not been partially breached, breached, or removed. Reservoirs can be drained permanently such as during dam removal, or temporarily, such as during dam rehabilitation.
Embankment means an artificially constructed feature usually consisting of earth and rock with sloping sides and a flat crest, intended to provide a permanent barrier that impounds or is capable of impounding water.
Emergency includes, but is not limited to, dam failures and all conditions leading to or causing a dam failure, including overtopping, or any other condition of a dam and its appurtenant structures that may be construed by the Department as hazardous or threatening to life or property.
Emergency Action Plan means a written plan that identifies the area that would likely be inundated by the failure of a dam, and identifies the actions that should be taken by the Owner to protect life, property, lifelines, and the environment in the event of a dam failure or threatening condition at the dam. The plan is usually implemented in cooperation with the local, regional, and state emergency personnel.
Engineer means a professional engineer licensed under Title 26 who has experience in the design and investigation of dams.
Environmental Loss means damage to the natural environment resulting from the failure or mis-operation of a dam, including damage to aquatic biota and habitat. Only the incremental damage caused by dam failure or mis-operation is considered. Environmental losses are considered "reversible" if they are expected to self-remediate within five years.
Federal dam means a dam owned by the United States or a dam subject to Federal Energy Regulatory Commission license or exemption.
Flashboard means a section (board) of timber, concrete, metal, inflatable bladder, etc. placed on the crest of a spillway to raise the water level, but that is designed to either be quickly removed in the event of a storm or deliberately designed to fail under storm loading.
Freeboard means the vertical distance between the dam crest and the reservoir water surface.
Hazard creep means the increase in hazard potential due primarily to new development downstream of existing dams that was not present during original design and construction or has increased since the dam's hazard classification was last evaluated.
Hazard Potential means the potential for incremental damages that could result from the release of water or stored contents due to failure of the dam or mis-operation of the dam or its appurtenances. The hazard potential classification of a dam is based on the potential loss of life, and damage to property, lifelines, and the environment resulting from dam failure, and does not reflect in any way on the current condition of the dam and its appurtenant structures.
HIGH Hazard Potential Dam mean dams where failure or mis-operation will probably cause loss of human life.
Hydraulic Height-of-dam means the vertical distance from the lowest point in the stream bed or native ground surface at the downstream toe of the dam to the elevation of the normal pool or water level in the reservoir.
Hydrologic and Hydraulic Analysis or "H&H" means the analytical process of computing the inflow to a reservoir and outflow from a dam under normal and storm conditions. This also includes the analyses of intermediary flood events and the means of managing flows during the construction, rehabilitation, or removal of a dam. Such analyses are used to determine normal and maximum reservoir pools, dam crest, spillway, and low-level outlet design requirements.
In-Service Dam means a dam that is currently retaining water, liquid, or sediment as originally designed.
Incremental damage means under the same conditions (e.g., flood, earthquake, or other event), the difference in impacts that would occur due to failure or mis-operation of the dam as opposed to those that would have occurred without failure or mis-operation of the dam and appurtenances
Inspection means the examination of a dam to determine its condition and need for improved operation, maintenance, study and analyses, repairs, rehabilitation, and or removal.
Instrumentation means an arrangement of devices (e.g. piezometers, inclinometers, weirs, etc.) installed into or near a dam which provide for measurements that can be used to evaluate the structural behavior and performance of a dam.
Intake structure means a dam that is constructed and operated for the primary purposes of minimally impounding water for the measurement and withdrawal of streamflow to ensure use of the withdrawn water for snowmaking, potable water, irrigation, or other purposes approved by the Department.
Interested person means, in relation to any dam, a person: who has riparian rights affected by that dam; who has a substantial interest in economic or recreational activity affected by the dam; or whose safety would be endangered by a failure of the dam.
Inundation Map means a map delineating the area that could be flooded by a particular flood event and dam failure condition.
Invert means the base level of a weir, pipe, tunnel, or penetration.
Lifeline means a structure or service indispensable for maintaining or protecting life, including but not limited to key transportation links such as bridges or highways; power supply lines; potable water connection or supply; or sanitary sewer connection.
LOW Hazard Potential Dam means dams where failure or mis-operation results in no probable loss of human life and low economic and environmental losses
Low-level outlet or "LLO" means an installed pipe and operable gate or valve typically located in or near the foundation of a dam that can be used to alter water levels, drain the reservoir, or otherwise meet operational or safety needs. Also called a pond drain.
Maximum Pool means the highest water elevation, reservoir surface area, and reservoir storage capacity that could be impounded by the dam, including accumulated sediments, with the water or liquid level at the top of the lowest nonoverflow part of the structure or dam crest.
MINIMAL Hazard Potential Dam means dams that impound or are capable of impounding less than 500,000 cubic feet (11.48 acre-feet) of water, other liquid, and/or sediment and meet the LOW hazard potential dam definition above.
Non-federal dam means a dam that is not a federal dam.
Non-power dam means any dam that is not a power dam.
Normal Pool means the water elevation, reservoir surface area, and reservoir storage capacity that is prevalent at the site or typical under normal, non-storm conditions. Typically, this level is controlled by the principal spillway.
Order means an official document prepared by the Department authorizing a dam owner to construct, enlarge, raise, lower, remodel, remove, reconstruct, or otherwise alter any nonfederal dam, pond, or impoundment or other structure that is or will be capable of impounding more than 500,000 cubic feet of water or other liquid after construction or alteration, pursuant to 10 V.S.A. § 1082.
Owner means a person owning legal title to a dam or the owner of the land on which a dam is located.
Operation and Maintenance Plan or "O&M" means a plan that provides guidelines for the necessary, regular operation and maintenance activities at a dam.
Parti ally Breached Dam means a dam that is no longer capable of impounding its normal pool under normal conditions but may still partially impound the reservoir, and has a hydraulic height greater than zero under mean annual flows (i.e. normally maintains a partially filled reservoir). A portion of the dam structure that impacts flow remains in place.
Person means any individual; partnership; company; corporation; association; joint venture; trust; municipality; the State of Vermont or any agency, department, or subdivision of the State; any federal agency; or any other legal or commercial entity.
Potential Failure Mode Analysis means the development and evaluation of possible modes of partial or full failure at a dam.
Power dam means a dam that relates to or is incident to the generation of electrical energy for public use or as part of a public utility system.
Principal spillway means a structure that maintains normal pool conditions and over which daily non- storm related and flood flows are discharged. Also called a primary or service spillway.
Probably/probable means more likely than not to occur; expected; realistic.
Property Loss means direct and indirect economic losses due to flood-damaged property or infrastructure located downstream of a dam, as a result of dam failure.
Removed Dam means the location where a dam once existed but is now a free-flowing stream with no remaining remnants of the dam in place that could impound water.
Reservoir means any area which contains or will contain impounded water, wastewater, or liquid-borne materials by virtue of its having been impounded by a dam. Also referred to as impoundment.
SIGNIFICANT Hazard Potential Dam means dams where failure or mis-operation results in no probable loss of human life but can cause economic loss, environmental damage, disruption of lifeline facilities, or impact other concerns. Significant hazard potential classification dams are often located in predominantly rural or agricultural areas but could be located in areas with population and significant infrastructure.
Spillway Crest means the invert elevation of the subject spillway.
Spillway Design Flood or "SDF " means the storm event which the hydraulic capacity of the spillway structure and dam is designed and required to safely pass.
Stoplog means a section of timber, concrete or steel placed in a slot or channel to maintain normal pool conditions but that can be removed to alter water levels, drain the reservoir, or otherwise meet operational or safety needs.
Structural Height-of-dam means the vertical distance from the lowest point in the stream bed or native ground surface at the downstream toe of the dam to the elevation of the lowest nonoverflow section of the dam crest.
Toe-of-dam means the junction of the downstream slope or face of a dam with the native ground surface or the invert out of the low-level outlet, whichever occurs at the lowest point.
Unsafe Dam means a dam that has been determined to be unsafe via Unsafe Dam Proceedings.
Unsafe Dam Order means an order issued by the Department as a result of an Unsafe Dam Proceeding, directing reconstruction, repair, removal, breaching, draining, or other action the Department considers necessary to improve the safety of the dam sufficiently to protect life and property.
Unsafe Dam Proceedings means dam safety proceedings carried out pursuant to 10 V.S.A. § 1095.
Wastewater means sanitary waste or used water from any building or structure or campground, including, but not limited to, carriage water, toilet water, shower and wash water, food processing wastewater, and process wastewater. Wastewater does not include stormwater.
The following general provisions shall apply to this rule:
This rule shall apply to non-federal, non-power dams in the State of Vermont under jurisdiction of the Agency of Natural Resources, Department of Environmental Conservation (the Department). It applies to dam registration, classification, inspection, application and approval to construct, re-construct, alter, repair, breach, or remove a dam, as well as related standards including design standards, operation and maintenance standards, inspection standards, and Emergency Action Plans. This rule shall not apply to dams owned and operated by the United States government or dams subject to a Federal Energy Regulatory Commission license or exemption (power and/or federal dams), or dams under the jurisdiction of the Vermont Public Utility Commission (power dams).
This includes costs associated with operation, maintenance, inspection, registration, compliance with standards, engineering study and design, risk assessment, permitting, Emergency Action Planning, repairs, reconstruction, and removal. Inability to meet the financial obligations associated with maintaining a dam in safe condition may result in the Department requiring the impoundment to be drained.
The Dam Record Form will not be deemed complete unless and until all information required by the Department has been supplied by the subject dam owner. For dams with multiple owners, all owners must submit a Dam Record Form.
Classification |
General Definition |
HIGH |
Dams where failure or mis-operation will probably cause loss of human life. |
SIGNIFICANT |
Dams where failure or mis-operation results in no probable loss of human life but can cause economic loss, environment damage, disruption of lifeline facilities, or impact other concerns. Significant hazard potential classification dams are often located in predominantly rural or agricultural areas but could be located in areas with population and significant infrastructure. |
LOW |
Dams where failure or mis-operation results in no probable loss of human life and low economic and environmental losses. |
MINIMAL |
A dam that meets the LOW hazard definition, above, but is only capable of impounding less than 500,000 cubic feet. |
The following additional guidance is provided and shall apply to dams subject to this rule:
Classification 1 |
Direct Loss of Life |
Property Losses |
Lifeline Losses |
Environmental Losses |
HIGH |
Probable or Certain (one or more) (extensive downstream residential, commercial, or industrial development) |
Not considered for this classification |
Not considered for this classification |
Not considered for this classification |
SIGNIFICANT |
None expected |
Major or extensive public and private facilities |
Disruption of essential or critical facilities and access |
Major or extensive mitigation required or impossible to mitigate |
LOW |
None expected |
Private agricultural lands, equipment and isolated non-occupied buildings, non-major roads |
No disruption of services - repairs are cosmetic or rapidly repairable damage |
Minimal incremental damage |
MINIMAL |
Same as LOW hazard, above |
|||
1) Categories are based on overall dam performance and do not apply to appurtenances. |
Dam inspections shall be performed under the supervision of an engineer. Inspections shall be performed in compliance with Department requirements by the Department or an engineer hired by the owner.
Periodic Inspections (1) |
|
Hazard Classification |
Frequency |
HIGH |
2 years |
SIGNIFICANT |
5 years |
LOW |
10 years |
MINIMAL |
None |
(1) The first inspection shall be performed when initiated or required by the Department and subsequent inspections shall be performed in compliance with the table above. |
Comprehensive inspections shall be performed:
The first comprehensive inspection shall be performed when initiated or required by the Department and subsequent inspections shall be performed in compliance with the time frames established above.
The Department shall review the request and any available information on the dam. If the Department determines that an inspection is required, the Department shall schedule an inspection of the dam with the owner.
For the purposes of this rule, financial assurance means a dam owner establishes and maintains financial security that is payable to the Department in an amount sufficient to pay for the breach or removal of the dam by the Department, should such breach or removal be deemed necessary. The amount of the financial security is sufficient if it can adequately cover the costs associated with a breach or removal of the dam, including the costs of investigation, design, permitting, and construction; and any other appropriate cost as determined by the Department. The form of the financial security shall be one or more of the following: a surety bond guaranteeing performance; one or more irrevocable letters of credit, payable to or at the direction of the Department; a trust fund established for the benefit of the Department; a policy of insurance that provides the Department with acceptable rights as a beneficiary thereof and that is issued by an insurance carrier whose operations are subject to regulation and examination by a State agency; one or more annuities; or one or more certificates of deposit; any other form which the Department determines to be acceptable.
Prior to performing any work on a dam capable of impounding more than 500,000 cubic feet, the owner shall complete and submit a Dam Order Application so that the Department can determine jurisdiction relative to the proposed activity. The application shall meet the content and format requirements of the Department.
Violations of any portion of this rule are subject to enforcement under applicable Vermont law, including 10 V.S.A Chapter 43 and 10 V.S.A Chapters 201 and 211. Failure to maintain and operate a dam in accordance with the standards provided in this rule shall constitute a violation of this rule.
Dam owners have primary responsibility for determining when an emergency involving a dam or reservoir under their ownership exists. When the owner of a dam or reservoir determines an emergency exists, the owner shall immediately implement the Emergency Action Plan, contact emergency management organizations to notify any persons who may be endangered should the dam fail, notify the Department, and take actions necessary to safeguard life, and health. A Dam Order as required under § 37-112 is not required to undertake emergency actions regulated in this section.
If a dam presents an imminent threat to human life or property, as determined by a dam owner or the Department following an investigation conducted pursuant to an Unsafe Dam Proceeding, and necessary actions are not being taken by the owner in the judgment of the Department, the Department may take such action as necessary to protect life and property. In taking emergency action, the Department may:
The Department may maintain full control over the dam until it is rendered safe or the emergency has ceased, and the owner is able to resume control of operations. The Department's take-over of the dam shall not relieve the owner of a dam of ownership or legal liability to the Department or third parties for damages resulting from dam failure. The Departments' assumption of control over the dam shall not constitute a taking and the Department shall not be liable to the dam owner or others for diminution in property value that may be caused by the Department's work.
The cost and expense of the remedial means provided herein, including cost of any work done to render a dam safe, may be collected by presentation of bills to owners in the same manner as other debts to the State are recoverable. If such bills are not promptly paid by the owner, the cost shall be recovered by the State from the owner by action brought by the Department in a court of appropriate jurisdiction. After taking whatever actions necessary to protect life and property and render the dam safe, the Department shall subsequently conduct an Unsafe Dam hearing.
If any section, subsection, division or subdivision of this rule shall be determined to be invalid, such determination shall apply only to the particular section, subsection, division, or subdivision, and all other provisions shall remain in full force and effect.
Notes
August 1, 2020 Secretary of State Rule Log #20-032
STATUTORY AUTHORITY:
10 V.S.A. § 1110
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.