Wash. Admin. Code § 365-230-340 - Recordkeeping and reporting requirements
(1) Firms performing renovations must retain
and, if requested, make available to the department all records necessary to
demonstrate compliance with this section for a period of three years following
completion of the renovation. This three-year retention requirement does not
supersede longer obligations required by other provisions for retaining the
same documentation, including any applicable state or tribal laws or
regulations.
(2) Records that must
be retained pursuant to subsection (a) of this section shall include (where
applicable):
(a) Records or reports certifying
that a determination had been made that lead-based paint was not present on the
components affected by the renovation, as described under WAC
365-230-300. These records or
reports include:
(i) Reports prepared by a
certified inspector or certified risk assessor (certified pursuant to this
chapter).
(ii) Records prepared by
a certified renovator after using EPA-recognized test kits, including an
identification of the manufacturer and model of any test kits used, a
description of the components that were tested including their locations, and
the result of each test kit used.
(iii) Records prepared by a certified
renovator after collecting paint chip samples, including a description of the
components that were tested including their locations, the name and address of
the NLLAP-recognized entity performing the analysis, and the results for each
sample.
(b) Signed and
dated acknowledgments of receipt as described under WAC
365-230-320(1)(a)(i) and (b)(i), (2)(a)(i),
(3)(a)(i)(A) and (a)(ii)(A).
(c) Certifications of attempted delivery as
described under WAC
365-230-320(1)(a)(i) and
(3)(a)(ii)(A).
(d) Certificates of mailing as described
under WAC
365-230-320(1)(a)(ii) and (b)(ii), (2)(a)(ii),
(3)(a)(i)(B) and (a)(ii)(B).
(e) Records of notification activities
performed regarding common area renovations, as described under WAC
365-230-320(2)(c) and
(d), and renovations in child-occupied
facilities, as described under WAC
365-230-320(3)(b).
(f) Documentation of compliance with the
requirements under WAC
365-230-330, including
documentation that a certified renovator was assigned to the project, that the
certified renovator provided on-the-job training for workers used on the
project, that the certified renovator performed or directed workers who
performed all of the tasks described under WAC
365-230-330(1),
and that the certified renovator performed the postrenovation cleaning
verification described under WAC
365-230-330(2).
If the renovation firm was unable to comply with all of the requirements of
this rule due to an emergency as defined under WAC
365-230-330, the firm must
document the nature of the emergency and the provisions of the rule that were
not followed. This documentation must include a copy of the certified
renovator's training certificate, and a certification by the certified
renovator assigned to the project that:
(i)
Training was provided to workers (topics must be identified for each
worker).
(ii) Warning signs were
posted at the entrances to the work area.
(iii) If test kits were used, that the
specified brand of kits was used at the specified locations and that the
results were as specified.
(iv) If
paint chip samples were collected, that the samples were collected at the
specified locations, that the specified NLLAP-recognized laboratory analyzed
the samples, and that the results were as specified.
(v) The work area was contained by:
(A) Removing or covering all objects in the
work area (interiors).
(B) Closing
and covering all HVAC ducts in the work area (interiors).
(C) Closing all windows in the work area
(interiors) or closing all windows in and within twenty feet of the work area
(exteriors).
(D) Closing and
sealing all doors in the work area (interiors) or closing and sealing all doors
in and within twenty feet of the work area (exteriors).
(E) Covering doors in the work area that were
being used to allow passage but prevent spread of dust.
(F) Covering the floor surface, including
installed carpet, with taped-down plastic sheeting or other impermeable
material in the work area six feet beyond the perimeter of surfaces undergoing
renovation or a sufficient distance to contain the dust, whichever is greater
(interiors) or covering the ground with plastic sheeting or other disposable
impermeable material anchored to the building extending ten feet beyond the
perimeter of surfaces undergoing renovation or a sufficient distance to collect
falling paint debris, whichever is greater, unless the property line prevents
ten feet of such ground covering, weighted down by heavy objects
(exteriors).
(G) Installing (if
necessary) vertical containment to prevent migration of dust and debris to
adjacent property (exteriors).
(vi) Waste was contained on-site and while
being transported off-site.
(vii)
The work area was properly cleaned after the renovation by:
(A) Picking up all chips and debris, misting
protective sheeting, folding it dirty side inward, and taping it for
removal.
(B) Cleaning the work area
surfaces and objects using a HEPA vacuum and/or wet cloths or mops
(interiors).
(viii) The
certified renovator performed the postrenovation cleaning verification (the
results of which must be briefly described, including the number of wet and dry
cloths used).
(3)
(a) When
the final invoice for the renovation is delivered or within thirty days of the
completion of the renovation, whichever is earlier, the renovation firm must
provide information pertaining to compliance with this section to the following
persons.
(i) The owner of the building; and,
if different;
(ii) An adult
occupant of the residential dwelling, if the renovation took place within a
residential dwelling, or an adult representative of the child-occupied
facility, if the renovation took place within a child-occupied
facility.
(b) When
performing renovations in common areas of multiunit target housing, renovation
firms must post the information required by this section or instructions on how
interested occupants can obtain a copy of this information. This information
must be posted in areas where it is likely to be seen by the occupants of all
of the affected units.
(c) The
information required to be provided by this subsection may be provided by
completing the sample form titled "Sample Renovation Recordkeeping Checklist"
or a similar form containing the test kit information required under subsection
(2)(a)(ii) of this section and the training and work practice compliance
information required under subsection (2)(f) of this section.
(4) If dust clearance sampling is
performed in lieu of cleaning verification as permitted under WAC
365-230-330(3),
the renovation firm must provide, when the final invoice for the renovation is
delivered or within thirty days of the completion of the renovation, whichever
is earlier, a copy of the dust sampling report to:
(a) The owner of the building; and, if
different;
(b) An adult occupant of
the residential dwelling, if the renovation took place within a residential
dwelling, or an adult representative of the child-occupied facility, if the
renovation took place within a child-occupied facility;
(c) When performing renovations in common
areas of multiunit target housing, renovation firms must post these dust
sampling reports or information on how interested occupants of the housing
being renovated can obtain a copy of the report. This information must be
posted in areas where they are likely to be seen by the occupants of all the
affected units.
Notes
Statutory Authority: RCW 70.103.10 [70.103.010], 70.103.20 [70.103.020], 70.103.30 [70.103.030], 70.103.40 [70.103.040],70.103.50 [70.103.050], 70.10.80 [70.103.080], and 70.103.90 [70.103.090]. 11-07-067, § 365-230-340, filed 3/21/11, effective 4/21/11.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.