Any Chapter 3 permit-to-construct issued for facilities subject to this chapter prior to the effective date of these regulations, and any facility authorized under the Division's "General Permit to Construct, Install, Modify or Operate a Small Wastewater Facility" shall remain covered under those permits. New construction or modification of existing facilities following the effective date of this regulation must obtain authorization under a new permit.

Notes

020-25 Wyo. Code R. §§ 25-3
Amended, Eff. 7/27/2016. Amended, Eff. 6/29/2018.