045-6 Wyo. Code R. §§ 6-6 - Attachment to Proposed Bridges or Structures

(a) General.

The provisions of Paragraph (i) & (ii). Section 5(a) apply.

(b) New Construction, Utility has Prior Right.

When the construction of a new bridge or structure forces the relocation of a utility facility and this relocation is reimbursable, the facility may be attached to the new structure provided the provisions of Chapter IV and Chapter VI, Section 5 can be met.

The Bridge Department will contact the utility during preliminary engineering and enter into an "Authority for Rendering Special Services" (ARS) with the utility. The cost of design, materials, and installation will be billed to the utility as those phases are completed.

Reimbursements due the utility for the bridge attachment shall be prorated by the utility based on the cost of the attachment versus the cost of not attaching to the bridge, and shown in the final billing to the Department for all of the reimbursable work on the project.

(c) New Construction, Utility by License.

When the construction of a new bridge or structure conflicts with an existing utility fine that is located on public R/W or otherwise has no reimbursable right; or

If a utility company wishes to attach facilities to a bridge or structure for other reasons, provided the criteria of Section 5 can be met, the Bridge Department will design the appropriate hanger system for the facility and include the installation in the Departments construction contract.

The cost of design, materials, and installation will be billed to the utility company. The request for work and costs shall be covered by an "Authority for Rendering Special Services" (ARS).

Notes

045-6 Wyo. Code R. §§ 6-6

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.