060-14 Wyo. Code R. §§ 14-7 - Application Procedure

(a) Applications. Persons desiring permission to use state land for a temporary purpose as provided in this chapter shall submit to the Director a completed application, including the lessee comment form and the fee as established in Chapter 17.
(b) Preliminary Approval. With the exception of applications for exclusive outfitting/guiding permits filed pursuant to Section 8 of this chapter the Director shall preliminarily approve or disapprove the application no less than 20 days, nor more than 30 days, after receipt of a completed application. In no case shall the Director preliminarily approve the application unless the consideration required under Section 6 of this chapter has been received.
(c) Effect of Preliminary Approval. Upon preliminary approval of the application, the applicant may commence the permitted use. However, the applicant bears the risk that the Board may ultimately disapprove the application.
(d) Final Approval. The Board shall approve or disapprove the application at its next regular meeting following the Director's action under subsection (b) of this section. If the application is disapproved and no permitted use has occurred, the consideration collected under Section 6 of this chapter and any related surface impact payment collected by the lessee shall be returned to the applicant.

Notes

060-14 Wyo. Code R. §§ 14-7

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.