060-33 Wyo. Code R. §§ 33-6 - Evaluation Criteria
(a) Criteria. The
Board shall evaluate applications utilizing one or more of the following
criteria:
(i) The extent to which the
applicant's total proposed energy impacted road projects exceed fifteen percent
(15%) of the average total annual expenditures for road and bridge maintenance
and construction expenditures for the preceding five (5) years.
(ii) The extent of funding committed to the
project from all sources;
(iii)
Whether the applicant has demonstrated that is has pursued alternative methods
of funding including cost sharing from private sources;
(iv) Whether the applicant has funding for
the project from other than state grants;
(v) Whether the project is appropriately
sized in relation to the population to be served by the project;
(vi) The relative urgency of the
project;
(vii) Whether the
applicant is current on all its repayment obligations to the Board;
(viii) The extent to which the applicant is
utilizing, or plans to utilize, available and qualified Wyoming based
professional firms and contractors on the project;
(ix) The financial need of the applicant, as
determined by the Board;
(x) The
percentage of the applicant's population directly served by the
project;