060-37 Wyo. Code R. §§ 37-10 - Ineligible Project Costs
(a) The following
costs are ineligible:
(i) Costs related to any
other infrastructure needs of the community college that are not directly
associated with the development and construction, renovation, or capital
renewal of student dormitories;
(ii) Costs for preparation or presentation of
loan application;
(iii) Costs
incurred prior to loan award, except costs for architectural and engineering
design, surveying and environmental review, if required;
(iv) Engineering fees, including design,
inspection and contract administration costs, over fifteen percent (15%) of the
project cost;
(v) Markups by
engineers/architects of sub-contractor and other outside charges;
(vi) Costs for transportation, meals, lodging
and incidentals incurred offsite from the project or that exceeds the current
federal per diem reimbursement rate;
(vii) Costs associated with the borrower's
own employees and equipment;
(viii)
Costs for real property in excess of current fair market value and costs for an
amount of real property in excess of that needed for project
purposes;
(ix) Costs related to
issuance of bonds;
(x) Legal
fees;
(xi) Costs for sidewalks that
are owned or maintained by a private property owner; and
(xii) Costs for a contingency or extra work
allowance in excess of ten percent (10%) of estimated construction
costs.