060-38 Wyo. Code R. §§ 38-6 - Application Procedure
(a) Applications.
(i) Each applicant shall submit a written
loan application to the Office on the form furnished by the Office. Applicants
seeking a loan for an Airport Project shall also submit a copy of the
application to the Division. At a minimum, the application shall include:
(A) A signed resolution stating the amount of
the loan being requested, name of project and repayment source(s), and agreeing
to maintain the project for the life of the loan;
(B) A detailed project summary which includes
a breakdown of total project costs, a project timeline and proposed repayment
source(s);
(C) Commitment letters
from all funding sources, if applicable;
(D) Engineer's Feasibility
Statement;
(E) A formal maintenance
plan documenting how the borrower will adequately maintain the project for the
life of the loan;
(F) If the
applicant is a special district, documentation of the formation of the special
district and certification by the Board of County Commissioners that the
special district currently exits; and
(G) If the applicant is a Joint Powers Board,
a copy of the joint powers agreement approved by the Attorney General and a
copy of the certification of organization filed with the Secretary of
State.
(ii) Incomplete
applications shall not be submitted to the Board for consideration.
(iii) Any false or misleading statements made
by the applicant in an application shall be grounds for summary rejection of
the application.
(iv) Timing.
(A) All loan applications must be received by
the Office at least ninety (90) calendar days prior to any regularly scheduled
meeting of the Board. Applicants must cure any defects in their application no
later than forty-five (45) calendar days before any regularly scheduled meeting
of the Board.
(B) Applications for
Airport Projects loans must also be received by the Division at least fifteen
(15) working days before a regular Commission meeting prior to the Board
meeting to consider the Loan.
(b) Consideration.
(i) The Office shall conduct a preliminary
review of all applications received. If the Office identifies issues with the
application which would result in a negative recommendation to the Board, the
Office shall notify the applicant within 30 days of receiving the application
of the issue and the applicant shall have the opportunity to correct the
application or withdraw the application. Applicants must cure any defects in
their application no later than forty-five (45) calendar days before any
regularly scheduled meeting of the Board. The Office may summarily reject any
applications with uncured defects or that are otherwise clearly
ineligible.
(ii) All applications
shall be reviewed by the Attorney General to certify the legality of the
transaction and to determine if an election is required by law.
(iii) The following will be considered when
reviewing applications:
(A) The project's
contribution to health, safety and welfare of the citizens in the political
subdivision as demonstrated by:
(I) The extent
the project will protect the citizens from exposure to hazards that may result
in adverse consequences;
(II)
Achieving compliance with state and federal mandates; or
(III) Any other relevant information
demonstrating the project's contribution to the health, safety and welfare of
the citizens.
(B) The
applicant's need for the project and financial need of the applicant in
relation to the project; and
(C)
The applicant's ability to repay the loan.
(iv) For applications for Airport Project
loans, the Division shall evaluate the applications for airport related
projects and the Administrator shall formulate a recommendation the Commission
using the following criteria:
(A) Whether the
proposed project is in compliance with the current Division accepted Airport
Layout Plan and the overall development of the airport;
(B) Whether the applicant is meeting any and
all current and past repayment obligations to the Commission; and
(C) The proposed project's merit in relation
to the overall state system planning and its usefulness in achieving state
goals.
(v) For
applications for Airport Project loans, the Commission shall:
(A) Consider each airport loan project
application and allow for comments from the applicant and the Administrator of
the Division; and
(B) Make a
written recommendation to the Board whether to award a loan and documenting any
concerns. If the recommendation is to award a loan, the Commission shall
recommend the loan amount and comment on the appropriateness and nature of the
type of security offered for the loan.