060-24 Wyo. Code R. § 24-5 - Grant Eligibility

(a) Applicants. Incorporated cities and towns, counties, special districts and joint powers boards shall be eligible to apply for grants under this chapter provided the applicant is an "eligible applicant" as defined in Section 2(e). If the applicant is a special district or joint powers board, it must be legally formed and approved prior to receiving a grant award under this chapter.
(b) Purposes. Pursuant to W.S. 9-4-604 and Laws 2007, Chapter 136, Section 328(g),(j-n),(p-t) and Section 329 the Board shall fund consensus list grants to eligible applicants only when the board finds the grant is necessary to:
(i) Alleviate an emergency situation which poses a direct and immediate threat to health, safety or welfare;
(ii) Comply with a federal or state mandate;
(iii) Provide an essential public service. Essential public services include, but are not limited to capital construction, acquisition of capital equipment, public safety projects, housing related projects and road repair or construction.
(c) Maximum Grant Percentage. Cumulatively, the consensus list of projects is limited to a grant from this chapter not to exceed 75% of eligible project costs.
(d) Ineligible Project Costs. The following project costs shall be ineligible for reimbursement from grant funds and shall be ineligible to be counted toward the applicant's match:
(i) Costs for sidewalks that are owned or maintained by a private property owner;
(ii) Costs for tap fees, sewer and water fees, and plant investment fees;
(iii) Engineering fees, including design, inspection and contract administration costs, over twenty percent (20%) of project cost;
(iv) All non-cash costs except:
(A) Land, labor, materials, equipment, and services provided by the applicant, and used for project purposes based on actual, appraised or market value; and
(B) Land, labor, materials, equipment, and services provided to the applicant by others, at no cost to the applicant, and used for project purposes based on actual, appraised or market value.
(v) Costs for preparation or presentation of grant or loan applications for any source of funding;
(vi) Costs for transportation, meals and lodging incurred anywhere away from the site of the project;
(vii) Costs for furnishings;
(viii) Legal fees;
(ix) Costs related to issuance of bonds;
(x) Costs for real property in excess of current fair market value and/or costs for an amount of real property in excess of that needed for project purposes;
(xi) Costs to establish and form special districts or joint powers boards;
(xii) Costs incurred prior to grant award, except costs for architectural and engineering design or in emergency situations;
(xiii) Costs for a contingency or extra work allowance in excess of 10% of estimated construction costs.

Notes

060-24 Wyo. Code R. § 24-5

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.