Schedule A |
||||
---|---|---|---|---|
Long-term Schedule A contingent capacity and associated firm energy for offers of contracts to Boulder Canyon project contractors |
||||
Contractor |
Contingent capacity (kW) |
Firm energy (thousands of kWh) |
||
Summer |
Winter |
Total |
||
Metropolitan Water District of Southern California |
249,948 |
859,163 |
368,212 |
1,227,375 |
City of Los Angeles |
495,732 |
464,108 |
199,175 |
663,283 |
Southern California Edison Company |
280,245 |
166,712 |
71,448 |
238,160 |
City of Glendale |
18,178 |
45,028 |
19,297 |
64,325 |
City of Pasadena |
11,108 |
38,622 |
16,553 |
55,175 |
City of Burbank |
5,176 |
14,070 |
6,030 |
20,100 |
Arizona Power Authority |
190,869 |
429,582 |
184,107 |
613,689 |
Colorado River Commission of Nevada |
190,869 |
429,582 |
184,107 |
613,689 |
United States, for Boulder City |
20,198 |
53,200 |
22,800 |
76,000 |
Totals |
1,462,323 |
2,500,067 |
1,071,729 |
3,571,796 |
Schedule B |
||||
---|---|---|---|---|
Long-term Schedule B contingent capacity and associated firm energy for offers of contracts to Boulder Canyon project contractors |
||||
Contractor |
Contingent capacity (kW) |
Firm energy (thousands of kWh) |
||
Summer |
Winter |
Total |
||
City of Glendale |
2,020 |
2,749 |
1,194 |
3,943 |
City of Pasadena |
9,089 |
2,399 |
1,041 |
3,440 |
City of Burbank |
15,149 |
3,604 |
1,566 |
5,170 |
City of Anaheim |
40,396 |
34,442 |
14,958 |
49,400 |
City of Azusa |
4,039 |
3,312 |
1,438 |
4,750 |
City of Banning |
2,020 |
1,324 |
576 |
1,900 |
City of Colton |
3,030 |
2,650 |
1,150 |
3,800 |
City of Riverside |
30,296 |
25,831 |
11,219 |
37,050 |
City of Vernon |
22,218 |
18,546 |
8,054 |
26,600 |
Arizona |
189,860 |
140,600 |
60,800 |
201,400 |
Nevada |
189,860 |
273,600 |
117,800 |
391,400 |
Totals |
507,977 |
509,057 |
219,796 |
728,853 |
Schedule C |
|
---|---|
Excess Energy |
|
Priority of entitlement to excess energy |
State |
First: Meeting Arizona’s first priority right to delivery of excess energy which is equal in each year of operation to 200 million kilowatthours: Provided, That in the event excess energy in the amount of 200 million kilowatthours is not generated during any year of operation, Arizona shall accumulate a first right to delivery of excess energy subsequently generated in an amount not to exceed 600 million kilowatthours, inclusive of the current year’s 200 million kilowatthours. Said first right of delivery shall accrue at a rate of 200 million kilowatthours per year for each year excess energy in an amount of 200 million kilowatthours is not generated, less amounts of excess energy delivered |
Arizona |
Second: Meeting Hoover Dam contractual obligations under Schedule A of subsection (a)(1)(A), under Schedule B of subsection (a)(1)(B), and under Schedule D of subsection (a)(2), not exceeding 26 million kilowatthours in each year of operation |
Arizona, Nevada, and California |
Third: Meeting the energy requirements of the three States, such available excess energy to be divided equally among the States |
Arizona, Nevada, and California |
Schedule D |
||||
---|---|---|---|---|
Long-term Schedule D resource pool of contingent capacity and associated firm energy for new allottees |
||||
State |
Contingent capacity (kW) |
Firm energy (thousands of kWh) |
||
Summer |
Winter |
Total |
||
New Entities Allocated by the Secretary of Energy |
69,170 |
105,637 |
45,376 |
151,013 |
New Entities Allocated by State |
.............. |
............. |
............. |
............. |
Arizona |
11,510 |
17,580 |
7,533 |
25,113 |
California |
11,510 |
17,580 |
7,533 |
25,113 |
Nevada |
11,510 |
17,580 |
7,533 |
25,113 |
Totals |
103,700 |
158,377 |
67,975 |
226,352 |
Nothing in the Criteria shall be construed to prejudice any rights conferred by the Boulder Canyon Project Act, as amended and supplemented [43 U.S.C. 617 et seq.], on the holder of a contract described in subsection (a) of this section not in default thereunder on September 30, 2067.
If any existing contractor fails to accept an offered contract, the Secretary of Energy shall offer the contingent capacity and firm energy thus available first to other entities in the same State listed in Schedule A and Schedule B, second to other entities listed in Schedule A and Schedule B, third to other entities in the same State which receive contingent capacity and firm energy under subsection (a)(2) of this section, and last to other entities which receive contingent capacity and firm energy under subsection (a)(2) of this section.
Except with respect to energy purchased at the request of an allottee pursuant to subsection (a)(3), the obligation of the Secretary of Energy to deliver contingent capacity and firm energy pursuant to contracts entered into pursuant to this section shall be subject to availability of the water needed to produce such contingent capacity and firm energy. In the event that water is not available to produce the contingent capacity and firm energy set forth in Schedule A, Schedule B, and Schedule D, the Secretary of Energy shall adjust the contingent capacity and firm energy offered under those Schedules in the same proportion as those contractors’ allocations of Schedule A, Schedule B, and Schedule D contingent capacity and firm energy bears to the full rated contingent capacity and firm energy obligations.
The provisions of this section constitute an exercise by the Congress of the right reserved by it in section 5(b) of the Boulder Canyon Project Act, as amended and supplemented [43 U.S.C. 617d(b)], to prescribe terms and conditions for contracts for electrical energy generated at Hoover Dam. This section constitutes the exclusive method for disposing of capacity and energy from Hoover Dam for the period beginning October 1, 2017, and ending September 30, 2067.
It is the purpose of this subchapter to ensure that the rights of contractors for capacity and energy from the Boulder Canyon project for the period beginning October 1, 2017, and ending September 30, 2067, will vest with certainty and finality.