Within 20 days of receiving a project submission under paragraph (1), the Revitalization Coordinator shall, in consultation with the Governor, identify all Puerto Rico Agencies that will have a role in the permitting, approval, authorizing, or other activity related to the development of such project submission.
Not later than 20 days after receiving a project submission, each Puerto Rico Agency identified in paragraph (1) shall submit to the Revitalization Coordinator the Agency’s Expedited Permitting Process.
If a Puerto Rico Agency fails to provide an Expedited Permitting Process within 20 days of receiving a project submission, the Revitalization Coordinator shall consult with the Governor to develop within 20 days an Expedited Permitting Process for the Agency.
The Revitalization Coordinator shall require Puerto Rico Agencies to implement the Expedited Permitting Process for Critical Projects. Critical Projects shall be prioritized to the maximum extent possible in each Puerto Rico Agency regardless of any agreements transferring or delegating permitting authority to any other Territorial Instrumentality or municipality.
Immediately following the completion of the Critical Project Report, the Revitalization Coordinator shall make such Critical Project Report public and allow a period of 30 days for the submission of comments by residents of Puerto Rico specifically on matters relating to the designation of a project as a Critical Project. The Revitalization Coordinator shall respond to the comments within 30 days of closing the coming [2] period and make the responses publicly available.
Not later than 5 days after the Revitalization Coordinator has responded to the comments under paragraph (2), the Revitalization Coordinator shall submit the Critical Project Report to the Oversight Board.