ALASKA DEPARTMENT OF ENVIRONMENTAL
CONSERVATION, PETITIONER v. ENVIRON-
MENTAL
PROTECTION AGENCY et al.
ON WRIT OF CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT
[January 21, 2004]
Justice Ginsburg delivered the opinion of the Court.
This case concerns the authority of the Environmental Protection Agency (EPA or Agency) to enforce the provisions of the Clean Air Acts (CAA or Act) Prevention of Significant Deterioration (PSD) program. Under that program, no major air pollutant emitting facility may be constructed unless the facility is equipped with the best available control technology (BACT). As added by §165, 91 Stat. 735, and amended, 42 U.S.C. § 7475(a)(4). BACT, as defined in the CAA, means, for any major air pollutant emitting facility, an emission limitation based on the maximum degree of [pollutant] reduction which the permitting authority, on a case-by-case basis, taking into account energy, environmental, and economic impacts and other costs, determines is achievable for [the] facility . §7479(3).
Regarding EPA oversight, the Act includes a general instruction and one geared specifically to the PSD program. The general prescription, §113(a)(5) of the Act, authorizes EPA, when it finds that a State is not complying with a CAA requirement governing construction of a pollutant source, to issue an order prohibiting construction, to prescribe an administrative penalty, or to commence a civil action for injunctive relief. 42 U.S.C. § 7413(a). Directed specifically to the PSD program, CAA §167 instructs EPA to take such measures, including issuance of an order, or seeking injunctive relief, as necessary to prevent the construction of a major pollutant emitting facility that does not conform to the PSD requirements of the Act. 42 U.S.C. § 7477.
In the case before us, the permitting authority under §7479(3) is the State of Alaska, acting through Alaskas Department of Environmental Conservation (ADEC). The question presented is what role EPA has with respect to ADECs BACT determinations. Specifically, may EPA act to block construction of a new major pollutant emitting facility permitted by ADEC when EPA finds ADECs BACT determination unreasonable in light of the guides §7479(3) prescribes? We hold that the Act confers that checking authority on EPA.
I
A
Congress enacted the Clean Air Amendments of 1970, 84 Stat. 1676, 42 U.S.C. § 7401 et seq., in response to dissatisfaction with the progress of existing air pollution programs. Union Elec. Co. v. EPA, 427 U.S. 246, 249 (1976). The amendments aimed to guarantee the prompt attainment and maintenance of specified air quality standards. Ibid.; D. Currie, Air Pollution §1.13, p. 116 (1981) (summary of 1970 amendments). Added by the 1970 amendments, §§108(a) and 109(a) of the Act require EPA to publish lists of emissions that cause or contribute to air pollution which may reasonably be anticipated to endanger public health or welfare, and to promulgate primary and secondary national ambient air quality standards (NAAQS) for such pollutants. 42 U.S.C. § 7408(a) and 7409(a); Whitman v. American Trucking Assns., Inc., 531 U.S. 457, 462463 (2001). NAAQS define [the] levels of air quality that must be achieved to protect public health and welfare. R. Belden, Clean Air Act 6 (2001). The Agency published initial NAAQS in 1971, Union Elec., 427 U.S., at 251 (citing 40 CFR pt. 50 (1975)), and in 1985, NAAQS for the pollutant at issue in this case, nitrogen dioxide. 40 CFR § 50.11 (2002).1
Under §110 of the Act, also added in 1970, each State must submit for EPA approval a plan which provides for implementation, maintenance, and enforcement of [NAAQS]. 42 U.S.C. § 7410(a)(1); cf. §7410(c)(1) (EPA shall promulgate an implementation plan if the States plan is inadequate). Relevant to this case, EPA has approved Alaskas implementation plan. 48 Fed. Reg. 30626 (1983), as amended, 56 Fed. Reg. 19288 (1991); 40 CFR § 52.96(a) (2002). To gain EPA approval, a state implementation plan (SIP) must include enforceable emission limitations and other control measures, means, or techniques as may be necessary or appropriate to meet the applicable [CAA] requirements. 42 U.S.C. § 7410(a)(2)(A). While States have wide discretion in formulating their plans, Union Elec., 427 U.S., at 250, SIPs must include certain measures Congress specified to assure that national ambient air quality standards are achieved, 42 U.S.C. § 7410(a)(2)(C). Among those measures are permit provisions, §7475, basic to the administration of the program involved in this case, CAAs Prevention of Significant Deterioration of Air Quality (PSD) program.
The PSD requirements, enacted as part of 1977 amendments to the Act, Title I, §160 et seq., 91 Stat. 731, are designed to ensure that the air quality in attainment areas or areas that are already clean will not degrade, Belden, supra, p. 43. See 42 U.S.C. § 7470(1) (purpose of PSD program is to protect public health and welfare from any actual or potential adverse effect which in [EPAs] judgment may reasonably be anticipate[d] to occur from air pollution notwithstanding attainment and maintenance of all national ambient air quality standards). Before 1977, no CAA provision specifically addressed potential air quality deterioration in areas where pollutant levels were lower than the NAAQS. Alabama Power Co. v. Costle, 636 F.2d 323, 346347 (CADC 1979). Responding to litigation initiated by an environmental group,2 however, EPA issued regulations in 1974 requiring that SIPs include a PSD program. Id., at 347, and n. 18 (citing 39 Fed. Reg. 42510 (1974)). Three years later, Congress adopted the current PSD program. See S. Rep. No. 95127, p. 11 (1977) (Congress itself has a responsibility to delineate a policy for protecting clean air).
The PSD program imposes on States a regime governing areas designated pursuant to [42 U.S.C. § 7407] as attainment or unclassifiable. §7471.3 An attainment area is one in which the air meets the national primary or secondary ambient air quality standard for [a regulated pollutant]. §7407(d)(1)(A)(ii). Air in an unclassifiable area cannot be classified on the basis of available information as meeting or not meeting the national primary or secondary ambient air quality standard for the pollutant. §7407(d)(1)(A)(iii). Northwest Alaska, the region this case concerns, is classified as an attainment or unclassifiable area for nitrogen dioxide, 40 CFR § 81.302 (2002), therefore, the PSD program applies to emissions of that pollutant in the region. In 2002, the Agency reported that [a]ll areas of the country that once violated the NAAQS for [nitrogen dioxide] now meet that standard. EPA, Latest Findings on National Air Quality 7 (Aug. 2003).
Section 165 of the Act, 42 U.S.C. § 7475 installs a permitting requirement for any major emitting facility, defined to include any source emitting more than 250 tons of nitrogen oxides per year, §7479(1). No such facility may be constructed or modified unless a permit prescribing emission limitations has been issued for the facility. §7475(a)(1); see §7479(2)(C) (defining construction to include modification). Alaskas SIP imposes an analogous requirement. 18 Alaska Admin. Code §50.300(c)(1) (2003). Modifications to major emitting facilities that increase nitrogen oxide emissions in excess of 40 tons per year require a PSD permit. 40 CFR § 51.166(b)(23)(i) (2002); 18 Alaska Admin. Code §50.300(h)(3)(B)(ii) (2003).
The Act sets out preconditions for the issuance of PSD permits. Inter alia, no PSD permit may issue unless the proposed facility is subject to the best available control technology for each pollutant subject to [CAA] regulation emitted from [the] facility. 42 U.S.C. § 7475(a)(4). As described in the Acts definitional provisions, best available control technology (BACT) means:
[A]n emission limitation based on the maximum degree of reduction of each pollutant subject to regulation under this chapter emitted from or which results from any major emitting facility, which the permitting authority, on a case-by-case basis, taking into account energy, environmental, and economic impacts and other costs, determines is achievable for such facility through application of production processes and available methods, systems, and techniques . In no event shall application of best available control technology result in emissions of any pollutants which will exceed the emissions allowed by any applicable standard established pursuant to section 7411 or 7412 of this title [emission standards for new and existing stationary sources]. §7479(3).
40 CFR § 51.166(b)(12) (2002) (repeating statutory definition). Alaskas SIP contains provisions that track the statutory BACT requirement and definition. 18 Alaska Admin. Code §§50.310(d)(3) and 50.990(13) (2003). The State, with slightly variant terminology, defines BACT as the emission limitation that represents the maximum reduction achievable for each regulated air contaminant, taking into account energy, environmental and economic impacts, and other costs. Ibid. Under the federal Act, a limited class of sources must gain advance EPA approval for the BACT prescribed in the permit. 42 U.S.C. § 7475(a)(8).
CAA also provides that a PSD permit may issue only if a source will not cause, or contribute to, air pollution in excess of any maximum allowable increase or maximum allowable concentration for any pollutant or any NAAQS. §7475(a)(3). Congress left to the Agency the determination of most maximum allowable increases, or increments, in pollutants. EPA regulations have defined increments for nitrogen oxides. 40 CFR § 51.166(c) (2002). Typically, to demonstrate that increments will not be exceeded, applicants use mathematical models of pollutant plumes, their behavior, and their dispersion. Westbrook, Air Dispersion Models: Tools to Assess Impacts from Pollution Sources, 13 Natural Resources & Env. 546, 547548 (1999).
Among measures EPA may take to ensure compliance with the PSD program, two have special relevance here. The first prescription, §113(a)(5) of the Act, provides that [w]henever, on the basis of any available information, [EPA] finds that a State is not acting in compliance with any requirement or prohibition of the chapter relating to the construction of new sources or the modification of existing sources, EPA may issue an order prohibiting the construction or modification of any major stationary source in any area to which such requirement applies. 42 U.S.C. § 7413(a)(5)(A).4 The second measure, §167 of the Act, trains on enforcement of the PSD program; it requires EPA to take such measures, including issuance of an order, or seeking injunctive relief, as necessary to prevent the construction or modification of a major emitting facility which does not conform to the [PSD] requirements. §7477.
B
Teck Cominco Alaska, Inc. (Cominco), operates a zinc concentrate mine, the Red Dog Mine, in northwest Alaska approximately 100 miles north of the Arctic Circle and close to the native Alaskan villages of Kivalina and Noatak. App. to Pet. for Cert. 3a; Brief for Petitioner 8; Brief for Respondents 4. The mine is the regions largest private employer. Brief for Petitioner 9. It supplies a quarter of the areas wage base. Ibid. Cominco leases the land from the NANA Regional Corporation, an Alaskan corporation formed pursuant to the Alaska Native Claims Settlement Act, 85 Stat. 688, as amended, 43 U.S.C. § 1601 et seq. Brief for NANA Regional Corporation, Inc., as Amicus Curiae 12, 4.
In 1988, Cominco obtained authorization to operate the mine, a major emitting facility under the Act and Alaskas SIP. App. 106. The mines PSD permit authorized five 5,000 kilowatt Wartsila diesel electric generators, MG1 through MG5, subject to operating restrictions; two of the five generators were permitted to operate only in standby status. Ibid. Petitioner Alaska Department of Environmental Conservation (ADEC) issued a second PSD permit in 1994 allowing addition of a sixth full-time generator (MG6), removing standby status from MG2, and imposing a new operational cap that allowed all but one generator to run full time. Ibid.
In 1996, Cominco initiated a project, with funding from the State, to expand zinc production by 40%. Brief for Petitioner 5; Reply Brief for Petitioner 11, n. 9. Anticipating that the project would increase nitrogen oxide emissions by more than 40 tons per year, see supra, at 5, Cominco applied to ADEC for a PSD permit to allow, inter alia, increased electricity generation by its standby generator, MG5. App. 107108; App. to Pet. for Cert. 33a. On March 3, 1999, ADEC preliminarily proposed as BACT for MG5 the emission control technology known as selective catalytic reduction (SCR),5 which reduces nitrogen oxide emissions by 90%. App. 72, 108. In response, Cominco amended its application to add a seventh generator, MG17, and to propose as BACT an alternative control technologyLow NOx6that achieves a 30% reduction in nitrogen oxide pollutants. Brief for Respondents 5, and n. 1; App. 84.
On May 4, 1999, ADEC, in conjunction with Comincos representative, issued a first draft PSD permit and preliminary technical analysis report that concluded Low NOx was BACT for MG5 and MG17. Id., at 5595. To determine BACT, ADEC employed EPAs recommended top-down methodology, id., at 61:
In brief, the top-down process provides that all available control technologies be ranked in descending order of control effectiveness. The PSD applicant first examines the most stringentor topalternative. That alternative is established as BACT unless the applicant demonstrates, and the permitting authority in its informed judgment agrees, that technical considerations, or energy, environmental, or economic impacts justify a conclusion that the most stringent technology is not achievable in that case. If the most stringent technology is eliminated in this fashion, then the next most stringent alternative is considered, and so on. EPA, New Source Review Workshop Manual B2 (Draft Oct. 1990) (hereinafter New Source Review Manual); App. 6162.7
Applying top-down methodology, ADEC
first homed in on SCR as BACT for MG5, and the new
generator, MG
17. [W]ith an estimated reduction
of 90%, ADEC stated, SCR is the most
stringent technology. Id., at 79. Finding SCR
technically and economically feasible, id.,
at 65, ADEC characterized as overstated
Comincos cost estimate of $5,643 per ton of nitrogen
oxide removed by SCR. Id., at 113. Using
Comincos data, ADEC reached a cost estimate running
between $1,586 and $2,279 per ton. Id., at 83. Costs
in that range, ADEC observed, are well within what ADEC
and EPA conside[r] economically feasible. Id., at
84. Responding to Comincos comments on the preliminary
permit, engineering staff in ADECs Air Permits Program
pointed out that, according to information Cominco provided to
ADEC, SCR has been installed on similar diesel-fired
engines throughout the world. Id., at 102.
Despite its staffs clear view that SCR (the most effective individual technology) [was] technologically, environmentally, and economically feasible for the Red Dog power plant engines, id., at 103104, ADEC endorsed the alternative proffered by Cominco. To achieve nitrogen oxide emission reductions commensurate with SCRs 90% impact, Cominco proposed fitting the new generator MG17 and the six existing generators with Low NOx. Ibid.8 Cominco asserted that it could lower net emissions by 396 tons per year if it fitted all seven generators with Low NOx rather than fitting two (MG5 and MG17) with SCR and choosing one of them as the standby unit. Id., at 87. Comincos proposal hinged on the assumption that under typical operating conditions one or more engines will not be running due to maintenance of standby-generation capacity. Ibid. If all seven generators ran continuously, however, Comincos alternative would increase emissions by 79 tons per year. Ibid. Accepting Comincos submission, ADEC stated that Comincos Low NOx solution achieve[d] a similar maximum NOx reduction as the most stringent controls; [could] potentially result in a greater NOx reduction; and is logistically and economically less onerous to Cominco. Id., at 8788.
On the final day of the public
comment period, July 2, 1999, the United States Department of
the Interior, National Parks Service (NPS), submitted comments
to ADEC. App. to Pet. for Cert. 33a; App. 97, 108. NPS
objected to the projected offset of new emissions from
MG5 and MG17 against emissions from other existing
generators that were not subject to BACT. Letter from John
Notar, NPS Air Resources Division, to Jim Baumgartner, ADEC
(June 2, 1999). Such an offset, NPS commented, is
neither allowed by BACT, nor achieves the degree of reduction
that would result if all the generators that are subject to
BACT were equipped with SCR. Id., at 3. NPS
further observed that the proposed production-increase project
would remove operating restrictions that the 1994 PSD permit
had placed on four of the existing generatorsMG1,
MG3, MG4, and MG5. App. to Pet. for Cert.
34a. Due to that alteration, NPS urged, those generators, too,
became part of the production-expansion project and would be
subject to the BACT
requirement. Ibid.
Following NPS lead, EPA wrote to ADEC on July 29, 1999, commenting: Although ADEC states in its analysis that [SCR], the most stringent level of control, is economically and technologically feasible, ADEC did not propose to require SCR . [O]nce it is determined that an emission unit is subject to BACT, the PSD program does not allow the imposition of a limit that is less stringent than BACT. App. 9697. A permitting authority, EPA agreed with NPS, could not offset new emissions by imposing new controls on other emission units that were not subject to BACT. Id., at 97. New emissions could be offset only against reduced emissions from sources covered by the same BACT authorization. Id., at 285286. EPA further agreed with NPS that, based on the existing information, BACT would be required for MG1, MG3, MG4, and MG5. Id., at 97.
After receiving EPA comments, ADEC issued a second draft PSD permit and technical analysis report on September 1, 1999, again finding Low NOx to be BACT for MG17. Id., at 105117. Abandoning the emissions-offsetting justification advanced in the May 4 draft permit, ADEC agreed with NPS and EPA that emission reductions from sources that were not part of the permit action, here MG1, MG2, MG3, MG4, MG5, and MG6, could not be considered in determining BACT for MG17. Id., at 111; id., at 199 (same).9
ADEC conceded that, lacking data from Cominco, it had made no judgment as to the impact of [SCR] on the operation, profitability, and competitiveness of the Red Dog Mine. Id., at 116. Contradicting its May 1999 conclusion that SCR was technically and economically feasible, see supra, at 10, ADEC found in September 1999 that SCR imposed a disproportionate cost on the mine. App. 116. ADEC concluded, on a cursory review, that requiring SCR for a rural Alaska utility would lead to a 20% price increase, and that in comparison with other BACT technologies, SCR came at a significantly higher cost. Ibid. No economic basis for a comparison between the mine and a rural utility appeared in ADECs technical analysis.
EPA protested the revised permit. In a September 15, 1999, letter, the Agency stated: Cominco has not adequately demonstrated any site-specific factors to support their claim that the installation of [SCR] is economically infeasible at the Red Dog Mine. Therefore, elimination of SCR as BACT based on cost-effectiveness grounds is not supported by the record and is clearly erroneous. Id., at 127; see id., at 138 (ADECs record does not support the departure from ADECs initial view that the costs for SCR were economically feasible).
To justify the September 1, 1999, permit, EPA suggested, ADEC could include an analysis of whether requiring Cominco to install and operate [SCR] would have any adverse economic impacts upon Cominco specifically. Id., at 127. Stating that such an inquiry was unnecessary and expressing concerns related to confidentiality, Cominco declined to submit financial data. Id., at 134. In this regard, Cominco simply asserted, without detail, that the companys overall debt remains quite high despite continuing profits. Id., at 134135. Cominco also invoked the need for [i]ndustrial development in rural Alaska. Id., at 135.
On December 10, 1999, ADEC issued the final permit and technical analysis report. Once again, ADEC approved Low NOx as BACT for MG17 [t]o support Comincos Red Dog Mine Production Rate Increase Project, and its contributions to the region. Id., at 208. ADEC did not include the economic analysis EPA had suggested. Id., at 152246. Indeed, ADEC conceded again that it had made no judgment as to the impact of [SCRs] cost on the operation, profitability, and competitiveness of the Red Dog Mine. Id., at 207. Nonetheless, ADEC advanced, as cause for its decision, SCRs adverse effect on the mines unique and continuing impact on the economic diversity of th[e] region and on the ventures world competitiveness. Id., at 208. ADEC did not explain how its inferences of adverse effects on the regions economy or the mines world competitiveness could be made without financial information showing SCRs impact on the operation, profitability, and competitiveness of the mine. Id., at 207, 299. Instead, ADEC reiterated its rural Alaska utility analogy, and again compared SCRs cost to the costs of other, less stringent, control technologies. Id., at 205207.
The same day, December 10, 1999, EPA issued an order to ADEC, under §§113(a)(5) and 167 of the Act, 42 U.S.C. § 7413(a)(5) and 7477, prohibiting ADEC from issuing a PSD permit to Cominco unless ADEC satisfactorily documents why SCR is not BACT for the Wartsila diesel generator [MG17]. App. to Pet. for Cert. 36a. In the letter accompanying the order, the Agency stated that ADECs own analysis supports the determination that BACT is [SCR], and that ADECs decision in the proposed permit therefore is both arbitrary and erroneous. App. 149.
On February 8, 2000, EPA, again invoking its authority under §§113(a)(5) and 167 of the Act, issued a second order, this time prohibiting Cominco from beginning construction or modification activities at the Red Dog mine. App. to Pet. for Cert. 49a. A third order, issued on March 7, 2000, superseding and vacating the February 8 order, generally prohibited Cominco from acting on ADECs December 10 PSD permit but allowed limited summer construction. Id., at 62a64a. On April 25, 2000, EPA withdrew its December 10 order. App. 300; App. to Pet. for Cert. 6a. Once ADEC issued the permit, EPA explained, that order lacked utility. On July 16, 2003, ADEC granted Cominco a PSD permit to construct MG17 with SCR as BACT. Letter from Theodore B. Olson, Solicitor General, to William K. Suter, Clerk of the Court (Aug. 21, 2003). Under the July 16, 2003, permit, SCR ceases to be BACT if and when the case currently pending before the Supreme Court of the United States of America is decided in favor of the State of Alaska. ADEC, Air Quality Construction Permit, Final Technical Analysis Report, Permit No. 9932AC005, Revision 2, p. 7.
The day EPA issued its first order against Cominco, February 8, 2000, ADEC and Cominco petitioned the Court of Appeals for the Ninth Circuit for review of EPAs orders. App. 11. The Agency initially moved to dismiss, urging that the Court of Appeals lacked subject-matter jurisdiction. In an order released March 27, 2001, the Ninth Circuit concluded that it had adjudicatory authority pursuant to 42 U.S.C. § 7607(b)(1), which lodges jurisdiction over challenges to any final [EPA] action in the Courts of Appeals. Alaska v. United States EPA, 244 F.3d 748, 750751.10
The Court of Appeals resolved the merits in a judgment released July 30, 2002. 298 F.3d 814 (CA9). It held that EPA had authority under §§113(a)(5) and 167 to issue the contested orders, and that the Agency had properly exercised its discretion in doing so. Id., at 820823. Concerning EPAs authority under §§113(a)(5) and 167, the Court of Appeals observed first that the question presented is what requirements the state must meet under the Act to issue a PSD permit, not what the correct BACT might be. Id., at 821 (emphasis in original). Concluding that EPA had authority to determine the reasonableness or adequacy of the states justification for its decision, the Court of Appeals emphasized that the provision of a reasoned justification by a permitting authority is undeniably a requirement of the Act. Ibid. EPA had properly exercised its discretion in issuing the three orders, the Ninth Circuit ultimately determined, because (1) Cominco failed to demonstrat[e] that SCR was economically infeasible, and (2) ADEC failed to provide a reasoned justification for its elimination of SCR as a control option. Id., at 823. We granted certiorari, 537 U.S. 1186 (2003), to resolve an important question of federal law, i.e., the scope of EPAs authority under §§113(a)(5) and 167, and now affirm the Ninth Circuits judgment.
II
ADEC contested EPAs orders under 42 U.S.C. § 7607(b)(1), which renders reviewable in the appropriate federal court of appeals any EPA final action. Before the Ninth Circuit, EPA unsuccessfully urged that its orders were interlocutory, and therefore unreviewable in court unless and until EPA chose to commence an enforcement action.11 A pre-enforcement contest could be maintained in the Court of Appeals under §7607(b)(1), the Ninth Circuit held, for in the circumstances presented, EPAs actions had the requisite finality.
It was undisputed, the Court of Appeals
observed, that EPA had spoken its
In this Court, EPA agrees with the Ninth Circuits finality determination. See Brief for Respondents 1620; Tr. of Oral Arg. 4344. We are satisfied that the Court of Appeals correctly applied the guides we set out in Bennett v. Spear, 520 U.S. 154, 177178 (1997) (to be final, agency action must mark the consummation of the agencys decisionmaking process, and must either determine rights or obligations or occasion legal consequences (internal quotation marks omitted)). As the Court of Appeals stated, EPA had asserted its final position on the factual circumstances underpinning the Agencys orders, 244 F.3d, at 750, and if EPAs orders survived judicial review, Cominco could not escape the practical and legal consequences (lost costs and vulnerability to penalties) of any ADEC-permitted construction Cominco endeavored, ibid.
No question has been raised here, we note, about the adequacy of EPAs preorder procedures under the Due Process Clause or the Administrative Procedure Act. Cf. Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U.S. 519, 544 (1978) (agencies have authority to fashion their own rules of procedure, even when a statute does not specify what process to use). Furthermore, in response to ADECs initial contention that the record was incomplete, the Ninth Circuit gave EPA an opportunity to supplement the record, and thereafter obtained from all parties agreement that the record as it stood was adequate to resolve [ADECs review petition]. 298 F.3d, at 818.
III
A
Centrally at issue in this case is the question whether EPAs oversight role, described by Congress in CAA §§113(a)(5) and 167, see supra, at 7, extends to ensuring that a state permitting authoritys BACT determination is reasonable in light of the statutory guides. Sections 113(a)(5) and 167 lodge in the Agency encompassing supervisory responsibility over the construction and modification of pollutant emitting facilities in areas covered by the PSD program. 42 U.S.C. § 7413(a)(5) and 7477. In notably capacious terms, Congress armed EPA with authority to issue orders stopping construction when a State is not acting in compliance with any [CAA] requirement or prohibition relating to the construction of new sources or the modification of existing sources, §7413(a)(5), or when construction or modification of a major emitting facility does not conform to the requirements of [the PSD program], §7477.
The federal Act enumerates several [p]reconstruction requirements for the PSD program. §7475. Absent these, [n]o major emitting facility may be constructed. Ibid. One express preconstruction requirement is inclusion of a BACT determination in a facilitys PSD permit. §§7475(a)(1) and (4). As earlier set out, see supra, at 56, the Act defines BACT as an emission limitation based on the maximum degree of reduction of [a] pollutant which the permitting authority, on a case-by-case basis, taking into account energy, environmental, and economic impacts and other costs, determines is achievable for [a] facility. §7479(3). Under this formulation, the permitting authority, ADEC here, exercises primary or initial responsibility for identifying BACT in line with the Acts definition of that term.
All parties agree that one of the many requirements in the PSD provisions that the EPA may enforce is that a [PSD] permit contain a BACT limitation. Brief for Petitioner 34; see id., at 22, 25 (same). See also Brief for Respondents 23. It is therefore undisputed that the Agency may issue an order to stop a facilitys construction if a PSD permit contains no BACT designation.
EPA reads the Acts definition of BACT, together with CAAs explicit listing of BACT as a [p]reconstruction requiremen[t], to mandate not simply a BACT designation, but a determination of BACT faithful to the statutes definition. In keeping with the broad oversight role §§113(a)(5) and 167 vest in EPA, the Agency maintains, it may review permits to ensure that a States BACT determination is reasonably moored to the Acts provisions. See id., at 24. We hold, as elaborated below, that the Agency has rationally construed the Acts text and that EPAs construction warrants our respect and approbation.
BACTs statutory definition requires selection of an emission control technology that results in the maximum reduction of a pollutant achievable for [a] facility in view of energy, environmental, and economic impacts, and other costs. 42 U.S.C. § 7479(3). This instruction, EPA submits, cabins state permitting authorities discretion by granting only authority to make reasonable BACT determinations, Brief for Respondents 27 (emphasis in original), i.e., decisions made with fidelity to the Acts purpose to insure that economic growth will occur in a manner consistent with the preservation of existing clean air resources, 42 U.S.C. § 7470(3). Noting that state permitting authorities statutory discretion is constrained by CAAs strong, normative terms maximum and achievable, §7479(3),12 EPA reads §§113(a)(5) and 167 to empower the federal Agency to check a state agencys unreasonably lax BACT designation. See Brief for Respondents 27.
EPA stresses Congress reason for enacting the PSD programto prevent significant deterioration of air quality in clean-air areas within a State and in neighboring States. §§7470(3), (4); see id., at 33. That aim, EPA urges, is unlikely to be realized absent an EPA surveillance role that extends to BACT determinations. The Agency notes in this regard a House Report observation:
Without national guidelines for the prevention of significant deterioration a State deciding to protect its clean air resources will face a double threat. The prospect is very real that such a State would lose existing industrial plants to more permissive States. But additionally the State will likely become the target of economic-environmental blackmail from new industrial plants that will play one State off against another with threats to locate in whichever State adopts the most permissive pollution controls. H. R. Rep. No. 95294, p. 134 (1977).
The House Report further observed that a community that sets and enforces strict standards may still find its air polluted from sources in another community or another State. Id., at 135 (quoting 116 Cong. Rec. 32909 (1970)). Federal agency surveillance of a States BACT designation is needed, EPA asserts, to restrain the interjurisdictional pressures to which Congress was alert. See Brief for Respondents 3334, 43; Brief for Vermont et al. as Amici Curiae 12 (If EPA has authority to ensure a reasonable level of consistency among BACT determinations nationwide, then every State can feel more confident about maintaining stringent standards without fear of losing its current industry or alienating prospective industry.).
The CAA construction EPA advances in
this litigation is reflected in interpretive guides the Agency
has several times published. See App. 268269 (1983 EPA
PSD guidance memorandum noting the Agencys
oversight function); id., at 274 (1988 EPA
guidance memorandum stating EPA may find a BACT determination
deficient if it is not based on a reasoned
analysis); id., at 281282 (1993 guidance
memorandum stating that EPA acts to ensure that the state
exercises its discretion within the bounds of the law
(internal quotation marks omitted); as to BACT, EPA will not
intervene if the state agency has given a reasoned
justification for the basis of its decision (internal
quotation marks omitted)). See also Approval and Promulgation
of Air Quality Implementation Plans; Commonwealth of
VirginiaPrevention of Significant Deterioration Program,
63 Fed. Reg. 13797 (1998) (EPA will review whether any
determination by the permitting authority was made on
reasonable grounds properly supported on the record, described
in enforceable terms, and consistent with all applicable
requirements). We normally accord particular
deference to an agency interpretation of
longstanding duration, Barnhart v.
Walton, 535
U.S. 212, 220 (2002) (quoting North Haven Bd. of Ed.
v. Bell, 456
U.S. 512, 522, n. 12 (1982)), recognizing that
well-reasoned views of an expert administrator rest
on
We have previously accorded dispositive effect to EPAs interpretation of an ambiguous CAA provision. See Chevron U.S. A. Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 865866 (1984); Union Elec., 427 U.S., at 256. The Agencys interpretation in this case, presented in internal guidance memoranda, however, does not qualify for the dispositive force described in Chevron. See Christensen v. Harris County, 529 U.S. 576, 587 (2000) (Interpretations such as those in policy statements, agency manuals, and enforcement guidelines, all of which lack the force of lawdo not warrant Chevron-style deference.); accord, United States v. Mead Corp., 533 U.S. 218, 234 (2001). Cogent administrative interpretations not [the] products of formal rulemaking nevertheless warrant respect. Washington State Dept. of Social and Health Servs. v. Guardianship Estate of Keffeler, 537 U.S. 371, 385 (2003). We accord EPAs reading of the relevant statutory provisions, §§7413(a)(5), 7470(3), 7470(4), 7475(a)(4), 7477, and 7479(3), that measure of respect.
B
ADEC assails the Agencys construction of the Act on several grounds. Its arguments do not persuade us to reject as impermissible EPAs longstanding, consistently maintained interpretation.
ADEC argues that the statutory definition of BACT, §7479(3), unambiguously assigns to the permitting authority alone determination of the control technology qualifying as best available. Brief for Petitioner 2126. Because the Act places responsibility for determining BACT with the permitting authority, ADEC urges, CAA excludes federal Agency surveillance reaching the substance of the BACT decision. Id., at 2225. EPAs enforcement role, ADEC maintains, is restricted to the requirement that the permit contain a BACT limitation. Id., at 34.
Understandably, Congress entrusted state permitting authorities with initial responsibility to make BACT determinations case-by-case. §7479(3). A state agency, no doubt, is best positioned to adjust for local differences in raw materials or plant configurations, differences that might make a technology unavailable in a particular area. But the fact that the relevant statutory guidesmaximum pollution reduction, considerations of energy, environmental, and economic impactsmay not yield a single, objectively correct BACT determination, id., at 23, surely does not signify that there can be no unreasonable determinations. Nor does Congress sensitivity to site-specific factors necessarily imply a design to preclude in this context meaningful EPA oversight under §§113(a)(5) and 167. EPA claims no prerogative to designate the correct BACT; the Agency asserts only the authority to guard against unreasonable designations. See 298 F.3d, at 821 (the question presented is what requirements the state must meet, not what final substantive decision the State must make (emphasis in original)).13
Under ADECs interpretation, EPA properly inquires whether a BACT determination appears in a PSD permit, Brief for Petitioner 34, but not whether that BACT determination was made on reasonable grounds properly supported on the record, 63 Fed. Reg., at 13797. Congress, however, vested EPA with explicit and sweeping authority to enforce CAA requirements relating to the construction and modification of sources under the PSD program, including BACT. We fail to see why Congress, having expressly endorsed an expansive surveillance role for EPA in two independent CAA provisions, would then implicitly preclude the Agency from verifying substantive compliance with the BACT provisions and, instead, limit EPAs superintendence to the insubstantial question whether the state permitting authority had uttered the key words BACT.
We emphasize, however, that
EPAs rendition of the Acts less than crystalline
text leaves the permitting authority considerable
leeway. The Agency acknowledges the need to accord
appropriate deference to States BACT designations,
Brief for Respondents 43, and disclaims any intention to
ADEC also points to 42 U.S.C. § 7475(a)(8), a provision of the Act expressly requiring, in a limited category of cases, EPA approval of a state permitting authoritys BACT determination before a facility may be constructed. See Brief for Petitioner 25; Reply Brief for Petitioner 6. Had Congress intended EPA superintendence of BACT determinations, ADEC urges, Congress would have said so expressly by mandating Agency approval of all, not merely some, BACT determinations. Brief for Petitioner 2526. ADECs argument overlooks the obvious difference between a statutory requirement, e.g., §7475(a)(8), and a statutory authorization. Sections 113(a)(5) and 167 sensibly do not require EPA approval of all state BACT determinations, they simply authorize EPA to act in the unusual case in which a state permitting authority has determined BACT arbitrarily. EPA recognizes that its authorization to issue a stop order may be exercised only when a state permitting authoritys decision is unreasonable; in contrast, a required approval may be withheld if EPA would come to a different determination on the merits. See, e.g., 57 Fed. Reg. 28095 (1992) (EPA acknowledges that states have the primary role in administering and enforcing the various components of the PSD program. States have been largely successful in this effort, and EPAs involvement in interpretative and enforcement issues is limited to only a small number of cases.).
Even if the Act imposes a requirement of reasoned justification for a BACT determination, ADEC ultimately argues, such a requirement may be enforced only through state administrative and judicial processes. Brief for Petitioner 3438.15 State review of BACT decisions, according to ADEC, allows development of an adequate factual record, properly imposes the burden of persuasion on EPA when it challenges a States BACT determination, and promotes certainty. Id., at 3637. Unless EPA review of BACT determinations is channeled into state administrative and judicial forums, ADEC suggests, there is nothing to prevent the EPA from invalidating a BACT determination at any timemonths, even years, after a permit has been issued. Id., at 35.
It would be unusual, to say the least, for Congress to remit a federal agency enforcing federal law solely to state court. We decline to read such an uncommon regime into the Acts silence. EPA, the expert federal agency charged with enforcing the Act, has interpreted the BACT provisions and its own §§113(a)(5) and 167 enforcement powers not to require recourse to state processes before stopping a facilitys construction. See supra, at 1721. That rational interpretation, we agree, is surely permissible.16
Nor are we persuaded by ADECs practical concerns. We see no reason to conclude that an appropriate record generally cannot be developed to allow informed federal-court review when EPA disputes a BACT decisions reasonableness. ADEC contends that, in this very case, the States BACT determination was reviewed by the Ninth Circuit on an incomplete record. Brief for Petitioner 37. ADEC, however, offers no particulars to back up its assertion that the Court of Appeals proceeded on an inadequate evidentiary record. We note again that the Ninth Circuit ordered EPA to submit a complete administrative record. 298 F.3d, at 818. After the Agency declared that the record was complete, all the parties effectively agreed that the record as it stood was adequate to resolve the issues on appeal. Ibid.
As to the burdens of production and persuasion, nothing in the Act suggests that EPA gains a proof-related tactical advantage by issuing a stop-construction order instead of seeking relief through a civil action. But cf. post, at 9 (EPA authority to issue stop-construction orders creates the anomaly of shifting the burden of pleading and of initiating litigation from EPA to the State). Correspondingly, nothing in our decision today invites or permits EPA to achieve an unfair advantage through its choice of litigation forum. In granting EPA a choice between initiating a civil action and exercising its stop-construction-order authority, see supra, at 7, 26, n. 15, Congress nowhere suggested that the allocation of proof burdens would differ depending upon which enforcement route EPA selected. The point ought not to be left in doubt. Accordingly, we hold that in either an EPA-initiated civil action or a challenge to an EPA stop-construction order filed in state or federal court, the production and persuasion burdens remain with EPA and the underlying question a reviewing court resolves remains the same: Whether the state agencys BACT determination was reasonable, in light of the statutory guides and the state administrative record. See supra, at 1819, 24.17
The Ninth Circuits review of EPAs order is in keeping with our holding that EPA may not reduce the burden it must carry by electing to invoke its stop-construction-order authority. Specifically, the Court of Appeals rested its judgment on what EPA showed from ADECs own report: (1) Cominco failed to meet its burden of demonstrating [to ADEC] that SCR was economically infeasible; and (2) ADEC failed to provide a reasoned justification for its elimination of SCR as a control option. 298 F.3d, at 823. EPAs conclusions, and the basis for them, support the Court of Appeals determination that the federal Agencys grounds for issuing the orders under review were not arbitrar[y] and capriciou[s]. Ibid. Our own analysis, infra at 3035, similarly hinges on the question whether ADECs BACT determination was a reasonable one. Our analysis would have taken the same path had EPA initiated a civil action pursuant to §113(a)(5)(C), or if the suit under consideration had been filed initially in state court.
Nor do we find compelling ADECs suggestion, reiterated by the dissent, that, if state courts are not the exclusive judicial arbiters, EPA would be free to invalidate a BACT determination months, even years, after a permit has been issued. Brief for Petitioner 35; post, at 1113. This case threatens no such development. It involves preconstruction orders issued by EPA, see supra, at 14, not postconstruction federal Agency directives. EPA itself regards it as imperative to act on a timely basis, recognizing that courts are less likely to require new sources to accept more stringent permit conditions the farther planning and construction have progressed. App. 273 (July 15, 1988, EPA guidance memorandum). In the one instance of untimely EPA action ADEC identifies, the federal courts declined to permit enforcement to proceed. See United States v. AM General Corp., 34 F.3d 472, 475 (CA7 1994) (affirming District Courts dismissal of an EPA-initiated enforcement action where EPA did not act until well after the facility received a PSD permit and completed plant modifications). EPA, we are confident, could not indulge in the inequitable conduct ADEC and the dissent hypothesize while the federal courts sit to review EPAs actions. Cf. Walz v. Tax Commn of City of New York, 397 U.S. 664, 678679 (1970); Panhandle Oil Co. v. Mississippi ex rel. Knox, 277 U.S. 218, 223 (1928) (Holmes, J., dissenting), overruled in part by Alabama v. King & Boozer, 314 U.S. 1, 89 (1941)).
In sum, EPA interprets the Act to allow substantive federal Agency surveillance of state permitting authorities BACT determinations subject to federal court review. We credit EPAs longstanding construction of the Act and confirm EPAs authority, pursuant to §§113(a)(5) and 167, to rule on the reasonableness of BACT decisions by state permitting authorities.
IV
A
We turn finally, and more
particularly, to the reasons why we conclude that EPA properly
exercised its statutory authority in this case. ADEC urges
that, even if the Act allows the Agency to issue
stop-construction orders when a state permitting authority
unreasonably determines BACT, EPA acted impermissibly in this
instance. See Brief for Petitioner 3948. We note,
first, EPAs threshold objection. ADECs petition to
this Court questioned whether the Act accorded EPA oversight
authority with respect to a States BACT determination.
Pet. for Cert. 1322. ADEC did not present, as a discrete
issue, the question whether EPA, assuming it had authority to
review the substance of a state BACT determination,
nevertheless abused its authority by countermanding ADECs
permit for the Red Dog Mine expansion. See Brief for
Respondents 4445; cf. Reply Brief for Petitioner
1516, n. 12 (EPA asserts authority to overturn
only arbitrary or unreasoned state BACT
determinations
. Thus, whether the State issued a
reasoned justification is fairly included within
the question presented[.]). Treating the case-specific
issue as embraced within the sole question presented, we are
satisfied that EPA did not act arbitrarily in finding that ADEC
furnished no tenable accounting for its determination that Low
NOx was BACT
for MG17.
Because the Act itself does not specify a standard for judicial review in this instance,18 we apply the familiar default standard of the Administrative Procedure Act, 5 U.S.C. § 706(2)(A), and ask whether the Agencys action was arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law. Even when an agency explains its decision with less than ideal clarity, a reviewing court will not upset the decision on that account if the agencys path may reasonably be discerned. Bowman Transp., Inc. v. Arkansas&nbhyph;Best Freight System, Inc., 419 U.S. 281, 286 (1974). EPAs three skeletal orders to ADEC and Cominco surely are not composed with ideal clarity. These orders, however, are properly read together with accompanying explanatory correspondence from EPA; so read, the Agencys comments and orders adequately ground the determination that ADECs acceptance of Low NOx for MG17 was unreasonable given the facts ADEC found.
In the two draft permits and the final permit, ADEC formally followed the EPA-recommended top-down methodology to determine BACT, as Cominco had done in its application. App. 61, 109, 175; see supra, at 910. Employing that methodology in the May 1999 draft permit, ADEC first concluded that SCR was the most stringent emission-control technology that was both technically and economically feasible. App. 65; see supra, at 910. That technology should have been designated BACT absent technical considerations, or energy, environmental, or economic impacts justif[ying] a conclusion that [SCR was] not achievable in [this] case. New Source Review Manual, p. B2; App. 6162. ADEC nevertheless selected Low NOx as BACT; ADEC did so in May 1999 based on Comincos suggestion that fitting all Red Dog Mine generators with Low NOx would reduce aggregate emissions. Id., at 87, 111112; see supra, at 1011.
In September and December 1999, ADEC again rejected SCR as BACT but no longer relied on Comincos suggestion that it could reduce aggregate emissions by equipping all generators with Low NOx. See supra, at 1214. ADEC candidly stated that it aimed [t]o support Comincos Red Dog Mine Production Rate Increase Project, and its contributions to the region. App. 208. In these second and third rounds, ADEC rested its selection of Low NOx squarely and solely on SCRs disproportionate cost. Id., at 116; id., at 112117, 203208; supra, at 1214.
EPA concluded that ADECs switch from finding SCR economically feasible in May 1999 to finding SCR economically infeasible in September 1999 had no factual basis in the record. See App. 138. In the September and December 1999 technical analyses, ADEC acknowledged that no judgment [could then] be made as to the impact of [SCRs] cost on the operation, profitability, and competitiveness of the Red Dog Mine. Id., at 116, 207. ADEC nevertheless concluded that SCR would threaten both the Red Dog Mines unique and continuing impact on the economic diversity of northwest Alaska and the mines world competitiveness. Id., at 208. ADEC also stressed the mines role as employer in an area with historical high unemployment and limited permanent year-round job opportunities. Id., at 207.
We do not see how ADEC, having acknowledged that no determination [could] be made as to the impact of [SCRs] cost on the operation and competitiveness of the [mine], ibid., could simultaneously proffer threats to the mines operation or competitiveness as reasons for declaring SCR economically infeasible. ADEC, indeed, forthrightly explained why it was disarmed from reaching any judgment on whether, or to what extent, implementation of SCR would adversely affect the mines operation or profitability: Cominco had declined to provide the relevant financial data, disputing the need for such information and citing confidentiality concerns, id., at 134; see supra, at 13; 298 F.3d, at 823 (Cominco failed to meet its burden of demonstrating that SCR was economically infeasible.). No record evidence suggests that the mine, were it to use SCR for its new generator, would be obliged to cut personnel, or raise zinc prices. Absent evidence of that order, ADEC lacked cause for selecting Low NOx as BACT based on the more stringent controls impact on the mines operation or competitiveness.
Nor has ADEC otherwise justified its choice of Low NOx. To bolster its assertion that SCR was too expensive, ADEC invoked four BACT determinations made in regard to diesel generators used for primary power production; BACTs cost, in those instances, ranged from $0 to $936 per ton of nitrogen oxide removed. App. 205206; supra, at 14. ADEC itself, however, had previously found SCRs per-ton cost, then estimated as $2,279, to be well within what ADEC and EPA considers economically feasible. App. 84; cf. id., at 204 (estimating SCRs per ton cost to be $2,100). No reasoned explanation for ADECs retreat from this position appears in the final permit. See id., at 138 ([SCRs cost falls] well within the range of costs EPA has seen permitting authorities nationwide accept as economically feasible for NOx control except where there are compelling site specific factors that indicate otherwise.). Tellingly, as to examples of low-cost BACT urged by Cominco, ADEC acknowledged: The cited examples of engines permitted in Alaska without requiring SCR are not valid examples as they either took place over 18 months ago or were not used for similar purposes. Id., at 233234 (footnote omitted). ADEC added that it has indeed permitted [Alaska] projects requiring SCR. Id., at 234. Further, EPA rejected ADECs comparison between the mine and a rural utility, see supra, at 1213, because no facts exist to suggest that the economic impact of the incrementally higher cost of SCR on the worlds largest producer of zinc concentrates would be anything like its impact on a rural, non-profit utility that must pass costs on to a small base of individual consumers. Brief for Respondents 49; App. 138139 (similar observation in Nov. 10, 1999, EPA letter).
ADECs basis for selecting Low NOx thus reduces to a readiness [t]o support Comincos Red Dog Mine Production Rate Increase Project, and its contributions to the region. Id., at 208. This justification, however, hardly meets ADECs own standard of a source-specific economic impac[t] which demonstrate[s] [SCR] to be inappropriate as BACT. Id., at 177. In short, as the Ninth Circuit determined, EPA validly issued stop orders because ADECs BACT designation simply did not qualify as reasonable in light of the statutory guides.
In its briefs to this Court, ADEC nonetheless justifies its selection of Low NOx as BACT for MG17 on the ground that lower aggregate emissions would result from Comincos agree[ment] to install Low NOx on all its generators. Brief for Petitioner 42, and n. 12 (emphasis added); id., at 29; Reply Brief for Petitioner 19, n. 16. We need not dwell on ADECs attempt to resurrect Comincos emissions-offsetting suggestion, see supra, at 1011, adopted in the initial May 1999 draft permit, but thereafter dropped. As ADEC acknowledges, the final PSD permit did not offset MG17s emissions against those of the mines six existing generators, installations that were not subject to BACT. Brief for Petitioner 42, n. 12; App. 149. ADEC recognized in September and December 1999 that a State may treat emissions from several pollutant sources as falling under one bubble19 for PSD permit purposes only if every pollutant source so aggregated is part of the permit action. Id., at 111, 199. Offsetting new emissions against those from any of the mines other generators, ADEC agreed, [was] not a consideration of the BACT review provided for by the applicable law or guidelines, for those generators remained outside the permits compass. Id., at 112, 199. ADEC plainly did not, and could not, base its December 10, 1999 permit and technical analysis on an emissions-offsetting rationale drawing in generators not subject to BACT. Id., at 111112.20 By that time, only MG17 was part of the permit action. Id., at 111, 199.
B
We emphasize that todays disposition does not impede ADEC from revisiting the BACT determination in question. In letters and orders throughout the permitting process, EPA repeatedly commented that it was open to ADEC to prepare an appropriate record supporting its selection of Low NOx as BACT. Tr. of Oral Arg. 35; see App. 127 (attachment to Sept. 28, 1999, EPA letter to ADEC, stating an analysis of whether requiring Cominco to install and operate [SCR] would have any adverse economic impacts upon Cominco specifically might demonstrate SCRs economic infeasibility); id., at 150 (letter accompanying EPAs Dec. 10, 1999, finding of noncompliance and order reiterating the Agencys willingness to review and consider any additional information or analyses provided by ADEC or Cominco on Low NOx as BACT); App. to Pet. for Cert. 36a (EPA Dec. 10, 1999, order inviting ADEC to justify its choice of Low NOx by document[ing] why SCR is not BACT [for MG17]); id., at 49a (similar statement in Feb. 8, 2000, order). At oral argument, counsel for EPA reaffirmed that, absolutely, ADEC could reconsider the matter and, on an appropriate record, endeavor to support Low NOx as BACT. Tr. of Oral Arg. 35.21 We see no reason not to take EPA at its word.
* *
In sum, we conclude that EPA has supervisory authority over the reasonableness of state permitting authorities BACT determinations and may issue a stop construction order, under §§113(a)(5) and 167, if a BACT selection is not reasonable. We further conclude that, in exercising that authority, the Agency did not act arbitrarily or capriciously in finding that ADECs BACT decision in this instance lacked evidentiary support. EPAs orders, therefore, were neither arbitrary nor capricious. The judgment of the Court of Appeals is accordingly
Affirmed.
Notes
1. Emissions levels for nitrogen dioxide, a regulated pollutant under the Act, are defined in terms of quantities of all oxides of nitrogen. R. Belden, Clean Air Act 47, n. 11 (2001). The term nitrogen oxides refers to a family of compounds of nitrogen and oxygen. The principal nitrogen oxides component present in the atmosphere at any time is nitrogen dioxides. Combustion sources emit mostly nitric oxide, with some nitrogen dioxide. Upon entering the atmosphere, the nitric oxide changes rapidly, mostly to nitrogen dioxide. EPA, Prevention of Significant Deterioration for Nitrogen Oxides, 53 Fed. Reg. 40656 (1988). Nitrogen oxides are also termed NOx.
2. Sierra Club v. Ruckelshaus, 344 F. Supp. 253 (DC 1972), affd per curiam, 4 E. R. C. 1815, 2 Env. L. Rep. 20656 (CADC 1972), affd by an equally divided court sub nom. Fri v. Sierra Club, 412 U.S. 541 (1973).
3. The PSD program also requires visibility control measures, 42 U.S.C. § 74917492, not at issue in this case.
4. As enacted in 1977, §113(a)(5) extended only to solid waste combustion and sources in nonattainment areas. See Title I, §111(a), 91 Stat. 685. Congress extended §113(a)(5) in 1990 amendments to the Act to cover attainment areas, and thus to encompass enforcement of PSD permitting requirements. Title VII, 104 Stat. 2672.
5. SCR requires injections of ammonia or urea into the exhaust before the exhaust enters a catalyst bed made with vanadium, titanium, or platinum. The reduction reaction occurs when the flue gas passes over the catalyst bed where the NOx and ammonia combine to become nitrogen, oxygen, and water . App. 71.
6. In Low NOx, changes are made to a generator to improve fuel atomization and modify the combustion space to enhance the mixing of air and fuel. Id., at 75.
7. Nothing in the Act or its implementing regulations mandates top-down analysis. See 42 U.S.C. § 7479(3); 40 CFR § 52.21(j) (2002). EPA represents that permitting authorities commonly use top-down methodology. Brief for Respondents 3.
8. Two generators already were fitted with a technology called Fuel Injection Timing Retard that results in a 20% to 30% reduction in nitrogen oxide emissions. App. 7576, 86.
9. Rather than subject MG1, MG3, MG4, and MG5 to BACT, ADEC and Cominco agreed to permit conditions that would require low NOx controls on MG1, MG3, MG4, and MG5, and emission limits that reflect the previous bubbled limits. Under this approach, the permit would result in no increase in actual or allowable emissions from any of these engines and the installation of BACT would not be necessary for these four units. Id., at 149. EPA found no cause to question this ADEC-Cominco agreement. Ibid.
10. At oral argument, counsel for EPA confirmed that the Agency no longer questions the Court of Appeals adjudicatory authority, satisfied that the finality requirement was met because the stop-construction order imposed new legal obligations on Cominco. Tr. of Oral Arg. 4344 (punctuation omitted).
11. Such an action would lie in district court, under 42 U.S.C. § 7413(b).
12. Formulations similar to the BACT definitions maximum degree of [pollutant] reduction achievable appear in the Acts standards for new sources in nonattainment areas, 42 U.S.C. § 7501(3) and 7503(a)(2) (lowest achievable emission rate) (internal quotation marks omitted), and its technology-based standard for hazardous emissions, §7412(d)(2) (maximum degree of reduction achievable).
13. The dissent admonishes that a statute is to be read as a whole. Post, at 3 (quoting King v. St. Vincents Hospital, 502 U.S. 215, 221 (1991)). We give that unexceptional principle effect by attending both to the unequivocal grant of supervisory authority to EPA in §§113(a)(5) and 167, and to the statutory control on permitting authorities discretion contained in the BACT definition, 42 U.S.C. § 7479(3). It is, moreover, a cardinal principle of statutory construction that a statute ought, upon the whole, to be so construed that, if it can be prevented, no clause, sentence, or word shall be superfluous, void, or insignificant. TRW Inc. v. Andrews, 534 U.S. 19, 31 (2001) (quoting Duncan v. Walker, 533 U.S. 167, 174 (2001)). The Act instructs permitting authorities to identify the best, maximum emission reduction technique, taking account of costs. 42 U.S.C. § 7479(3). The dissent does not explain how that instruction can be construed as something other than a constraint on permitting authorities discretion. Ultimately, the dissent recognizes the essential statutory requirement: selection of the technology that can best reduce pollution within practical constraints. Post, at 4 (emphasis added). Nor do we find enlightening Congress inclusion of the word determines in the BACT definition. Post, at 2. Even under the dissents view of the Act, state permitting authorities BACT determinations are not conclusiv[e] and authoritativ[e]. Ibid. (internal quotation marks and citation omitted). As the dissent develops at length, review of such BACT determinations may be sought in state court. Post, at 711; Alaska Stat. §44.62.560 (2002). And EPA actions, of course, are subject to the process of judicial review, see post, at 1, Congress empowered federal courts to provide, here in 42 U.S.C. § 7607(b)(1). See supra, at 1617.
14. According to the Agency, [i]t has proven to be relatively rare that a state agency has put EPA in the position of having to exercise [its] authority, noting that only two other reported judicial decisions concern EPA orders occasioned by States faulty BACT determinations. Brief for Respondents 30, and n. 9 (citing Allsteel, Inc. v. EPA, 25 F.3d 312 (CA6 1994), and Solar Turbines Inc. v. Seif, 879 F.2d 1073 (CA3 1989)). EPAs restrained and moderate use of its authority hardly supports the dissents speculation that the federal Agency will displac[e] or degrad[e] state agencies or relegate them to the performance of ministerial functions. Post, at 14, 1617. Nor has EPA ever asserted authority to override a state-court judgment. Cf. post, at 10. Preclusion principles, we note in this regard, unquestionably do apply against the United States, its agencies and officers. See, e.g., Montana v. United States, 440 U.S. 147 (1979).
15. From the availability of state-court judicial review, the dissent concludes, it necessarily follows that EPA must take the same procedural steps, of filing suit in state court, as any other person or entity seeking to challenge the issuance of a PSD permit. Post, at 8. Interpreted otherwise, the dissent asserts, the Act contains a loophole that allows an EPA end run around the States process. Post, at 10. In designing the Act, however, Congress often gave EPA a choice of enforcement measures. For example, EPA has three options to address a failure to comply with new source requirements. Compare 42 U.S.C. § 7413(a)(5)(A) (EPA may issue an order prohibiting the construction or modification of any major stationary source), with §7413(a)(5)(B) (EPA may issue an administrative penalty order), and §7413(a)(5)(C) (EPA may bring a civil action). Other sections of the Act provide EPA with similar options. See, e.g., §§7413(a)(1)(a)(3). Following the dissents logic, EPAs authority to bring a civil action would rule out, as a loophole, its authority to issue a stop-construction order. Moreover, the existence of concurrent authority is hardly at odds with the Act. As ADEC itself concedes, EPA can issue a checking order if a PSD permit lacks a BACT determination, Brief for Petitioner 34, even if state-court jurisdiction could be invoked instead.
16. Experience, we have already noted, see supra, at 2425, n. 14, affords no grounding for the dissents predictions that EPA oversight, which is undeniably subject to federal-court review, will rewor[k] the balance between State and Federal Governments and threaten state courts independence. Post, at 1012.
17. [L]ooking for the burden of pleading is not a foolproof guide to the allocation of the burdens of proof. The latter burdens do not invariably follow the pleadings. 2 J. Strong, McCormick on Evidence §337, pp. 411412 (5th ed. 1999). No single principle or rule solve[s] all cases and afford[s] a general test for ascertaining the incidence of proof burdens. 9 J. Wigmore, Evidence §2486, p. 288 (J. Chadbourn rev. ed. 1981) (emphasis deleted). [I]n a case of first impression, which we address today, reference to which party has pleaded a fact is no help at all. McCormick, supra, at 412. Among other considerations, allocations of burdens of production and persuasion may depend on which partyplaintiff or defendant, petitioner or respondenthas made the affirmative allegation or presumably has peculiar means of knowledge. Wigmore, supra, at 288, 290 (emphases deleted); accord, Campbell v. United States, 365 U.S. 85, 96 (1961).
18. The Court of Appeals referred to 42 U.S.C. § 7607(d)(9)(A) when it considered whether EPAs decision was arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law. 298 F.3d 814, 822 (CA9 2002). Section 7607(d)(9), however, applies only to the subsection concerning rulemaking in which it is embedded.
19. Cf. Chevron U.S. A. Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 853859 (1984) (upholding EPA regulations allowing States to treat all pollutant-emitting devices within the same stationary source in a nonattainment area as though encased in a single bubble).
20. The May 4, 1999, draft permit considered whether adding Low NOx to seven generators would result in lower emissions than adding SCR to only two and choosing one of the latter as a standby unit. App. 8687. Before December 10, 1999, however, Cominco agreed to install Low NOx controls on four of the mines six existing generatorsMG1, MG3, MG4, and MG5in order to increase use of those generators without exceeding the 1994 PSD permits operating restriction. Id., at 149. Having agreed to use Low NOx on four generators, Cominco could propose in the December 10, 1999, permit only the addition of Low NOx to two generatorsMG2 and MG6to offset increases in emissions from MG17. No facts in the record support any suggestion that addition of Low NOx to three generators, MG2, MG6, and MG17, would result in lower aggregate emissions than the addition of SCR to MG17 alone.
21. The dissent is daunted by the hypothesis that [b]ecause there can always be an additional procedure to ensure that the preceding process was followed, the State may never reach the goal of issuing a permit. Post, at 14 (The majority creates a sort of Zenos paradox for state agencies.). Again, the dissent can point to no instance in which EPA has indulged in any piling of process upon process. See supra, at 27, n. 16.