18 AAC 15.020 - Permit applications
(a) Except as provided in
18 AAC 15.130 -
18 AAC 15.140, an applicant for a
permit or written approval subject to
18 AAC 15.020 -
18 AAC 15.100 must serve a
complete application on the department.
(b) An applicant must serve a complete
application under (a) of this section for the department's review at least
(1) five days before the proposed
commencement of the operation, for applications for surface oiling
permits;
(2) 30 days before the
proposed commencement of construction, installation, modification, or
improvement, for applications for plan approvals or permits for a sewerage
system treatment works, or public water system;
(3) 60 days before the proposed commencement
of construction, installation, modification, or improvement, for applications
for plan approvals or permits for a municipal sewerage system, treatment works,
or public water system project that involves state or federal monetary
assistance;
(4) 60 days before the
proposed commencement of the operation, for an application for a solid waste
disposal permit, short-term variance form water quality standards, or
wastewater disposal permit; and
(5)
100 days before the proposed commencement of a pesticide use that requires a
permit under 18 AAC 90.
Notes
Authority:AS 46.03.020
AS 46.03.100
AS 46.03.110
AS 46.03.320
AS 46.03.330
AS 46.03.720
AS 46.03.730