Ill. Admin. Code tit. 62, § 1816.71 - Disposal of Excess Spoil: General Requirements
a) Excess spoil shall be placed in designated
disposal areas within a permit area, in a controlled manner to:
1) Minimize the adverse effects of leachate
and surface water runoff from the fill on surface and ground waters;
2) Ensure mass stability and prevent mass
movement during and after construction; and
3) Ensure that the final fill is suitable for
reclamation and revegetation compatible with the natural surroundings and the
approved post-mining land use.
b) Design certification.
1) The fill and appurtenant structures shall
be designed using current, prudent engineering practices. A qualified
registered professional engineer experienced in the design of earth and rock
fills shall seal the design of the fill and appurtenant structures.
2) The fill shall be designed to attain a
minimum long-term static safety factor of
1.5. The foundation and
abutments of the fill must be stable under all conditions of
construction.
c) All
vegetative and organic materials shall be removed from the disposal area prior
to placement of the excess spoil. Topsoil shall be removed, segregated, and
stored or replaced in accordance with Section
1816.22. If
approved by the Department, organic material may be used as mulch or may be
included in the topsoil to control erosion, promote growth of vegetation, or
increase the moisture retention of the soil.
d) Slope protection shall be provided to
minimize surface erosion at the site. All disturbed areas, including diversion
channels that are not riprapped, or otherwise protected from erosion, shall be
vegetated upon completion of construction.
e) The disposal areas shall be located on the
most moderately sloping and naturally stable areas available as approved by the
Department. Fill materials suitable for disposal shall be placed upon or above
a natural terrace, bench or berm if such placement provides additional
stability and prevents mass movement.
f) Excess spoil shall be transported and
placed in a controlled manner in horizontal lifts not exceeding four (4) feet
in thickness, concurrently compacted as necessary to ensure mass stability and
prevent mass movement during and after construction; graded so that surface and
subsurface drainage is compatible with the natural surroundings; and covered
with topsoil or substitute material in accordance with Section 1816.22. The
Department may approve a design which incorporates placement of excess spoil in
horizontal lifts other than four (4) feet in thickness when it is demonstrated
by the operator and sealed by a qualified registered professional engineer that
the design will ensure the stability of the fill and will meet all other
requirements of this Section.
g)
The final configuration of the fill must be suitable for the approved
post-mining land use. In addition:
1) No
permanent impoundments are allowed on the completed fill. Small depressions
shall be allowed by the Department if they are needed to retain moisture,
minimize erosion, create and enhance wildlife habitat, or assist revegetation,
and if they are not incompatible with the stability of the fill, as set forth
in Sections
1816.41(a),
1816.97(a)
and
1816.111;
2) Box cut spoils shall blend with
undisturbed land with a maximum outslope steepness of twenty-five (25) percent
(4h:lv);
3) Other direct cast spoil
placed onto unmined land shall be graded so as to reduce the slope to the
maximum extent by grading toward and over the mined area, and blending with the
unmined land with an outslope that does not exceed fifteen (15) percent;
and
4) Drainage from the interior
portion of the spoil shall not be directed over the outside slope of the box
cut spoil unless an erosion control system is designated to accommodate the
runoff from the interior area.
h) Terraces may be constructed on the
outslope of the fill if required for stability, control of erosion, to conserve
soil moisture, or to facilitate the approved post-mining land use, as set forth
in Sections
1816.41(a)
and
1816.111(a).
The grade of the outslope between terrace benches shall not be steeper than
2h:1v (fifty (50) percent). Terrace(s) are required where the vertical height
of the excess spoil exceeds forty (40) feet.
i) Where the slope in the disposal area
exceeds lv:2.8 h (thirty-six (36) percent), or such lesser slope designated by
the Department based on local conditions, keyway cuts (excavations to stable
bedrock) or rock toe buttresses shall be constructed to stabilize the fill.
Where the toe of the spoil rests on a downslope, stability analyses shall be
performed in accordance with 62 Ill. Adm. Code
1780.35(c)
to determine the size of rock toe buttresses and keyway cuts.
j) A qualified registered professional
engineer or other qualified professional specialist under the direction of a
registered professional engineer, experienced in the construction of earth and
rockfill embankments, shall periodically inspect the fill during construction.
Such inspections shall be made at least quarterly throughout construction and
during the critical construction periods. Critical construction periods shall
include at a minimum:
1)
A) Foundation preparation, including the
removal of all organic material and topsoil;
B) Placement of underdrain and protective
filter systems;
C) Installation of
final surface drainage systems; and
D) The final graded and revegetated
fill.
E) Regular inspections by the
engineer or specialist shall also be conducted during placement and compaction
of fill materials.
2)
The qualified registered professional engineer shall provide to the Department
a sealed report within two (2) weeks after each inspection that the fill has
been constructed and maintained as designed and in accordance with the approved
plan and 62 Ill. Adm. Code 1700 through 1850. The report shall include
appearances of instability, structural weakness and other hazardous
conditions.
3) The sealed report on
the drainage system and protective filters shall include color photographs of
the structure taken during and after construction, but before underdrains are
covered with excess spoil. If the underdrain system is constructed in phases,
each phase shall be sealed separately.
4) Where excess durable rock spoil is placed
in single or multiple lifts such that the underdrain system is constructed
simultaneously with excess spoil placement by the natural segregation of dumped
materials, in accordance with Section
1816.74,
color photographs shall be taken of the underdrain as the underdrain system is
being formed.
5) The photographs
accompanying each sealed report shall be taken in adequate size and number with
enough terrain or other physical features of the site shown to provide a
relative scale to the photographs and to specifically and clearly identify the
site.
6) A copy of each inspection
report shall be retained at or near the mine site.
k) Coal processing wastes shall not be
disposed of in head-of-hollow or valley fills, and may only be disposed of in
other excess spoil fills, if such waste is:
1)
Placed in accordance with Section
1816.83;
2) Demonstrated to be nontoxic- and
nonacid-forming; and
3)
Demonstrated to be consistent with the design stability of the fill.
l) Drainage control. If the
disposal area contains springs, natural or manmade watercourses, or wet-weather
seeps, the fill design shall include diversions and underdrains as necessary to
control erosion, prevent water infiltration into the fill, and ensure
stability.
1) Diversions shall comply with the
requirements of Section
1816.43.
2) Underdrains shall consist of durable rock
or pipe, be designed and constructed using current, prudent engineering
practices. The underdrain system shall be designed to carry the anticipated
seepage of water due to rainfall away from seeps and springs in the foundation
of the disposal area and shall be protected from piping and contamination by an
adequate filter. Rock underdrains shall be constructed of durable, nonacid-,
nontoxic-forming rock (e.g., natural sand and gravel, sandstone, limestone, or
other durable rock) that does not slake in water or degrade to soil
material,and which is free of coal, clay or other nondurable material.
Perforated pipe underdrains shall be corrosion resistant and shall have
characteristics consistent with the long-term life of the fill.
m) The foundation and abutments of
the fill shall be stable under all conditions of construction and operation.
Sufficient foundation investigation, as well as any necessary laboratory
testing of foundation materials, shall be performed in order to determine the
design requirements for stability of the foundation. Analyses of foundation
conditions shall include the effect of underground mine workings, if any, upon
the stability of the fill and appurtenant structures.
n) Excess spoil may be returned to
underground mine workings, but only in accordance with a disposal program
approved by the Department and MSHA under 62 Ill. Adm. Code
1784.25.
o) Excess spoil that is acid- or
toxic-forming or combustible shall be adequately covered with nonacid, nontoxic
and noncombustible material, or treated, to control the impact on surface and
ground water in accordance with Section 1816.41, to prevent sustained
combustion, and to minimize adverse effects on plant growth and the approved
post-mining land use as set forth in Section
1816.111(a).
Notes
Amended at 11 Ill. Reg. 8131, effective July 1, 1987