Ill. Admin. Code tit. 62, § 1817.43 - Diversions
a) General
Requirements.
1) With the approval of the
Department, any flow from mined areas abandoned before May 3, 1978, and any
flow from undisturbed areas or reclaimed areas, after meeting the criteria of
Section
1817.46
for siltation structure removal, may be diverted from disturbed areas by means
of temporary or permanent diversions. All diversions shall be designed to
minimize adverse impacts to the hydrologic balance within the permit and
adjacent areas, to prevent material damage outside the permit area and to
assure the safety of the public. Diversions shall not be used to divert water
into underground mines without approval of the Department under Section
1817.41(h).
2) The diversion and its appurtenant
structures shall be designed, located, constructed, maintained, and used to:
A) Be stable;
B) Provide protection against flooding and
resultant damage to life and property;
C) Prevent, to the extent possible using the
best technology currently available, additional contributions of suspended
solids to stream flow outside the permit area. Appropriate sediment control
measures for diversions may include, but not be limited to, maintenance of
appropriate gradients, channel lining, revegetation, roughness structures, and
detention basins; and
D) Comply
with the Rivers, Lakes, and Streams Act [615 ILCS 5 ], Section 404 of the
Federal Water Pollution Control Act of 1972, as amended ( 30 USC 1344), and
all local ordinances.
3)
Temporary diversions shall be removed promptly when no longer needed to achieve
the purpose for which they were authorized. The land disturbed by the removal
process shall be restored in accordance with this Part. Before diversions are
removed, downstream water - treatment facilities previously protected by the
diversion shall be modified or removed, as necessary, to prevent overtopping or
failure of the facilities. This requirement shall not relieve the permittee
from maintaining water treatment facilities as otherwise required. When
permanent diversions are constructed or stream channels restored prior to the
removal of temporary diversions the permittee shall:
A) Establish, restore, enhance where
practicable, or maintain natural riparian vegetation on the banks of the
stream, including any area that is subject to annual inundation;
B) Establish or restore the stream to its
natural meandering shape and to an environmentally acceptable gradient, as
determined by the Department; and
C) Establish or restore the stream to a
longitudinal profile and cross - section, including aquatic habitats (usually a
pattern of riffles, pools, and drops rather than uniform depth) that
approximate premining stream channel characteristics.
4) Diversion design shall incorporate the
following:
A) Channel lining shall be designed
using standard engineering practices to pass safely the design velocities.
Riprap shall consist of non-degradable, non-acid or toxic-forming rock such as
sandstone, limestone, or other durable rock that will not slake in water and
will be free of coal, clay or shale;
B) Freeboard shall be no less than 0.3 feet,
except as provided for in subsection (a)(5). Protection shall be provided for
transition of flows and for critical areas such as swales and curves. Where the
area protected is a critical area, as determined by the Department, the design
freeboard may be increased;
C)
Energy dissipators shall be installed, when necessary, at discharge points
where diversions intersect with natural streams and exit velocity of the
diversion ditch flow is greater than that of the receiving stream;
D) Excess excavated material not necessary
for diversion channel geometry or regrading of the channel shall be disposed of
in accordance with Sections
1817.71
through
1817.74;
and
E) Topsoil shall be handled in
compliance with Section
1817.22.
5) If the terrain is such that
out-of-bank flows can accommodate the design precipitation event without
endangering health or the environment as a result of flooding, such as physical
harm or slope failure, the need for diversion ditches may be modified by taking
into account channels, banks, and flood plains.
b) Diversions of perennial and intermittent
streams.
1) Diversions of perennial and
intermittent streams within the permit area are subject to Department approval
pursuant to Section
1817.57(a).
2) The design capacity of channels for
temporary and permanent stream channel diversions shall be at least equal to
the capacity of the unmodified stream channel immediately upstream and
downstream from the diversion.
3)
The requirements of subsection (a)(2)(B) shall be met when the temporary and
permanent diversions for perennial and intermittent streams are designed so
that the combination of channel, bank, and floodplain configuration is adequate
to pass safely the peak runoff of a 10 year, 6 hour precipitation event for a
temporary diversion and a 100 year, 6 hour precipitation event for a permanent
diversion.
4) The longitudinal
profile of the stream, the channel, and the floodplain shall be designed and
constructed to remain stable. Erosion control structures such as channel lining
structures, retention basins, and artificial channel roughness structures shall
be used in diversions only when approved by the Department as being necessary
to control erosion.
5) The design
and construction of all stream channel diversions of perennial and intermittent
streams shall be sealed by a qualified registered professional engineer as
meeting the performance standards of this Part.
c) Diversion of miscellaneous flows.
1) Miscellaneous flows, which consist of all
flows except for perennial and intermittent streams, may be diverted away from
disturbed areas if required or approved by the Department to lessen
environmental impact. Miscellaneous flows shall include ground water discharges
and ephemeral streams.
2) The
design, location, construction, maintenance, and removal of diversions of
miscellaneous flows shall meet all of the performance standards set forth in
subsection (a).
3) The requirements
of subsection (a)(2)(B) shall be met when the temporary and permanent
diversions for miscellaneous flows are designed so that the combination of
channel, bank, and floodplain configuration is adequate to pass safely the peak
runoff of a 2 year, 6 hour precipitation event for a temporary diversion and a
10 year, 6 hour precipitation event for a permanent diversion.
Notes
Amended at 29 Ill. Reg. 9829, effective June 27, 2005
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.