310 CMR 40.0465 - Utility-related Abatement Measures Status and Remedial Monitoring Reports
(1) Persons
conducting Utility-related Abatement Measures shall submit a Status Report to
the Department 120 days following notification to the Department of their
intentions to conduct a Utility-related Abatement Measure pursuant to
310
CMR 40.0462(1)(b), and every
six months thereafter, until a Utility-related Abatement Measure Completion
Report is submitted to the Department in accordance with
310
CMR 40.0466. Each Status Report shall
document Utility-related Abatement Measure activities occurring over the period
of time since the previously submitted Status Report.
(2) Utility-related Abatement Measure Status
Reports shall contain, at a minimum, the following information:
(a) the status of response
operations;
(b) any significant new
site information or data;
(c)
details of and/or plans for the management of Remediation Waste, Remedial
Wastewater and/or Remedial Additives;
(d) any other information required by the
Department pursuant to any condition that the Department imposes on the right
to conduct Utility-related Abatement Measures, pursuant to
310
CMR 40.0463(2);
and
(e) an LSP Opinion as to
whether the Utility-related Abatement Measure is being conducted in conformance
with the provisions of
310
CMR 40.0000 and any conditions established by
the Department.
(3)
Status Reports shall not be required for any Utility-related Abatement Measure
completed within 120 days following notification to the Department of the
intention to conduct the same, pursuant to
310
CMR 40.0462(1)(b).
(4) Utility-related Abatement Measure Status
Reports shall be submitted to the Department using a transmittal form
established by the Department for such purposes.
(5) For a disposal site where Active
Operation and Maintenance of a remedial action is being conducted as part of a
URAM, a Remedial Monitoring Report shall be submitted to the Department on a
form established by the Department for such purposes at a frequency of every
six months and concurrently with the submittal of the URAM Status Report. In
such cases when the Active Operation and Maintenance of a remedial action is
initiated after the submittal of the first URAM Status Report, the Remedial
Monitoring Report shall be submitted concurrently with the next URAM Status
Report.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
(1) Persons conducting Utility-related Abatement Measures shall submit a Status Report to the Department 120 days following notification to the Department of their intentions to conduct a Utility-related Abatement Measure pursuant to 310 CMR 40.0462(1)(b), and every six months thereafter, until a Utility-related Abatement Measure Completion Report is submitted to the Department in accordance with 310 CMR 40.0466. Each Status Report shall document Utility-related Abatement Measure activities occurring over the period of time since the previously submitted Status Report.
(2) Utility-related Abatement Measure Status Reports shall contain, at a minimum, the following information:
(a) the status of response operations;
(b) any significant new site information or data;
(c) details of and/or plans for the management of Remediation Waste, Remedial Wastewater and/or Remedial Additives;
(d) any other information required by the Department pursuant to any condition that the Department imposes on the right to conduct Utility-related Abatement Measures, pursuant to 310 CMR 40.0463(2); and
(e) an LSP Opinion as to whether the Utility-related Abatement Measure is being conducted in conformance with the provisions of 310 CMR 40.0000 and any conditions established by the Department.
(3) Status Reports shall not be required for any Utility-related Abatement Measure completed within 120 days following notification to the Department of the intention to conduct the same, pursuant to 310 CMR 40.0462(1)(b).
(4) Utility-related Abatement Measure Status Reports shall be submitted to the Department using a transmittal form established by the Department for such purposes.
(5) For a disposal site where Active Operation and Maintenance of a remedial action is being conducted as part of a URAM, a Remedial Monitoring Report shall be submitted to the Department on a form established by the Department for such purposes at a frequency of every six months and concurrently with the submittal of the URAM Status Report. In such cases when the Active Operation and Maintenance of a remedial action is initiated after the submittal of the first URAM Status Report, the Remedial Monitoring Report shall be submitted concurrently with the next URAM Status Report.