310 CMR 40.0466 - Utility-related Abatement Measure Completion Reports
(1) A Utility-related Abatement Measure
Completion Report shall be submitted to the Department within 60 days of the
completion of all response actions associated with a Utility-related Abatement
Measure.
(2) A Utility-related
Abatement Measure Completion Report shall contain, at a minimum, the following:
(a) a succinct summary of information and
data pertaining to the discovery, location and evaluation of encountered
contamination, and of all response actions undertaken and/or
completed;
(b) documentation on the
management of Remediation Waste, Remedial Additives and/or Remedial Wastewater
managed at the site; and
(c)
details on any proposed or ongoing active or passive remedial systems that will
remain in place at the site.
(3) Except as provided in 310 CMR 40.0466(4),
a Utility-related Abatement Measure shall not be considered complete until all
stockpiled/stored Remediation Waste generated as a result of the
Utility-related Abatement Measure is removed from the site pursuant to the
provisions of
310
CMR 40.0030.
(4) Remediation Waste may be stored, treated,
managed, disposed, recycled or reused at a site following the submission to the
Department of a Utility-related Abatement Measure Completion Report and
Completion Statement only if:
(a) such
actions are conducted in conformance with the provisions of
310
CMR 40.0030; and
(5) Except as
provided in 310 CMR 40.0466(6), Utility-related Abatement Measure Completion
Reports shall be submitted to the Department appended to a Completion Statement
form established by the Department for such purposes. The Completion Statement
form shall contain:
(a) an LSP Opinion on
whether the Utility-related Abatement Measure was conducted in accordance with
310
CMR 40.0460, and any approval conditions
specified by the Department; and
(b) the certification of the submittal
required by
310
CMR 40.0009.
(6) Notwithstanding the provisions of 310 CMR
40.0466(5), an LSP Opinion shall not be required for Utility-related Abatement
Measure Completion Reports documenting response actions at those
Utility-related Abatement Measures described at
310
CMR 40.0462(4).
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
(1) A Utility-related Abatement Measure Completion Report shall be submitted to the Department within 60 days of the completion of all response actions associated with a Utility-related Abatement Measure.
(2) A Utility-related Abatement Measure Completion Report shall contain, at a minimum, the following:
(a) a succinct summary of information and data pertaining to the discovery, location and evaluation of encountered contamination, and of all response actions undertaken and/or completed;
(b) documentation on the management of Remediation Waste, Remedial Additives and/or Remedial Wastewater managed at the site; and
(c) details on any proposed or ongoing active or passive remedial systems that will remain in place at the site.
(3) Except as provided in 310 CMR 40.0466(4), a Utility-related Abatement Measure shall not be considered complete until all stockpiled/stored Remediation Waste generated as a result of the Utility-related Abatement Measure is removed from the site pursuant to the provisions of 310 CMR 40.0030.
(4) Remediation Waste may be stored, treated, managed, disposed, recycled or reused at a site following the submission to the Department of a Utility-related Abatement Measure Completion Report and Completion Statement only if:
(a) such actions are conducted in conformance with the provisions of 310 CMR 40.0030; and
(5) Except as provided in 310 CMR 40.0466(6), Utility-related Abatement Measure Completion Reports shall be submitted to the Department appended to a Completion Statement form established by the Department for such purposes. The Completion Statement form shall contain:
(a) an LSP Opinion on whether the Utility-related Abatement Measure was conducted in accordance with 310 CMR 40.0460, and any approval conditions specified by the Department; and
(b) the certification of the submittal required by 310 CMR 40.0009.
(6) Notwithstanding the provisions of 310 CMR 40.0466(5), an LSP Opinion shall not be required for Utility-related Abatement Measure Completion Reports documenting response actions at those Utility-related Abatement Measures described at 310 CMR 40.0462(4).