Nev. Admin. Code § 459.95345 - Permit required for construction; preliminary meeting with Division

1. Before an owner or operator of a facility may commence the construction of a new process subject to C.A.P.P., the owner or operator must obtain a permit to construct the new process from the Division pursuant to NAC 459.95345 to 459.953467, inclusive.
2. Before applying for a permit to construct a new process, the owner or operator of the process must meet with the Division to discuss:
(a) The scope of the project and the applicable codes and standards relating to the design and construction of the project;
(b) The requirements for the submission of documents; and
(c) The schedule for the construction of the project.

Notes

Nev. Admin. Code § 459.95345
Added to NAC by Environmental Comm'n by R041-01, eff. 10-25-2001; A by R137-04, 2-15-2005

NRS 459.3818, 459.3829