Nev. Admin. Code § 459.953463 - Initial review of application for permit to construct; notification of applicant concerning completeness of application

1. Upon receipt of an application for a permit to construct a new process, the Division shall review the application to determine if the application includes all the information required by NAC 459.953451. Not later than 30 days after the date on which an application is received, the Division shall provide to the applicant its initial determination as to the completeness of the application.
2. If the Division determines that an application for a permit to construct does not include all the information required by NAC 459.953451, the Division shall notify the applicant of its determination and include in the notice a description or list of the deficiencies.
3. If the Division determines that an application for a permit to construct is not complete, the Division may:
(a) Return all the submitted information to the applicant and require the applicant to resubmit the application when completed; or
(b) Delay the review of the incomplete application until the applicant submits the required information and the application is determined to be complete.

Notes

Nev. Admin. Code § 459.953463
Added to NAC by Environmental Comm'n by R041-01, eff. 10-25-2001

NRS 459.3818, 459.3829

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.