Nev. Admin. Code § 459.953465 - Notice of receipt of application for permit to construct; period for public comment; action by Division after period of public comment
1. Upon determining that an application for a
permit to construct a new process is complete, the Division shall issue a
notice of its receipt of the application. The notice must:
(a) Be sent to the applicant and the local
governing body in the area in which the new process is to be located, and be
published on an Internet website designed to give general public notice;
and
(b) Summarize the review to be
conducted by the Division on the application for the permit to construct and
state that the following information will be available for public review:
(1) The registration submitted pursuant to
NAC 459.953451;
(2) The coordinated emergency plan
document;
(3) The site plan;
and
(4) A copy of the conditional
use permit.
2. The period for public comment must be 30
days and commences on the date on which the notice is published on an Internet
website pursuant to subsection 1.
3. Not later than 15 days after the date on
which the period for public comment concerning an application for a permit to
construct closes, the Division may, after considering the documents that are
part of the application, require further modifications if such modifications
are determined necessary to satisfy the requirements set forth in NAC
459.953467 for issuing a permit
to construct.