Ohio Admin. Code 3745-67-54 - Design and operating requirements

The owner or operator of each new waste pile on which construction commences after January 29, 1992, each lateral expansion of a waste pile unit on which construction commences after July 29, 1992, and each such replacement of an existing waste pile unit that is to commence reuse after July 29, 1992 must install two or more liners and a leachate collection and removal system above and between such liners, and operate the leachate collection and removal systems, in accordance with paragraph (C) of rule 3745-56-51 of the Administrative Code, unless exempted under paragraph (D), (E), or (F) of rule 3745-56-51 of the Administrative Code; and must comply with the procedures of paragraph (B) of rule 3745-67-21 of the Administrative Code."Construction commences" is as defined in rule 3745-50-10 of the Administrative Code under"existing facility".

Notes

Ohio Admin. Code 3745-67-54
Eff 12-30-89; Replaces old 3745-67-54, eff. 12-7-04
Rule promulgated under: RC 119.03
Rule authorized by: 3734.12
Rule amplifies: RC 3734.12
R.C. 119.032 review dates: Exempt

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.